{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "https://eldaddp.azurewebsites.net/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&dateTabled=2023-11-27", "definition" : "https://eldaddp.azurewebsites.net/meta/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&dateTabled=2023-11-27", "extendedMetadataVersion" : "https://eldaddp.azurewebsites.net/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&dateTabled=2023-11-27&_metadata=all", "first" : "https://eldaddp.azurewebsites.net/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&_page=0&dateTabled=2023-11-27", "hasPart" : "https://eldaddp.azurewebsites.net/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&dateTabled=2023-11-27", "isPartOf" : "https://eldaddp.azurewebsites.net/answeredquestions.text?tablingMemberPrinted.=Lord+Berkeley&dateTabled=2023-11-27", "items" : [{"_about" : "http://data.parliament.uk/resources/1672973", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672973/answer", "answerText" : {"_value" : "

There are currently 11% of lighting columns out of order on the M1 between Junctions 1- 6A and, 30.7% between Junctions 6A -10. Lighting columns are inspected every 28 days, and the repair of any faults varies depending on the nature and priority of the fault(s) in question. A typical simple fault will in most cases be repaired within 14 days.<\/p>

The lighting outages between M1 junctions 6a and 10 are the consequence of underground cable faults. Testing work is planned to take place in the next financial year, 2024-25, and will assess the condition of the cable network so that repairs can be prioritised alongside other asset needs.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-11T14:57:38.883Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Motorways: Lighting"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government what percentage of lamp columns on the M1 between junction 1 and junction 10 are out of light, how often lamp columns on motorways are inspected for such issues, and within what period of time they expect defective lamp columns on motorways to be repaired.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL579"} , {"_about" : "http://data.parliament.uk/resources/1672974", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672974/answer", "answerText" : {"_value" : "

Eight platforms are planned for Old Oak Common rail station on the Great Western Main Line. This consists of four relief line platforms and four main line platforms.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-06", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-06T15:08:28.26Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Old Oak Common Station: Great Western Main Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government how many platforms are planned for Old Oak Common rail station on the Great Western Main Line.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL580"} , {"_about" : "http://data.parliament.uk/resources/1672975", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672975/answer", "answerText" : {"_value" : "

Old Oak Common is being designed and built as a single, integrated station, with a budget of £1.67bn (Q3 2019). There is no separate cost for the conventional station. Enabling Works at Old Oak Common started in 2018 and permanent works started in 2020. The station works will continue until opening for passenger services in 2029-2033. The total time is therefore between 11 and 15 years.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-06", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-06T15:07:06.79Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Old Oak Common Station: Construction"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government what estimate they have made of (1) the total cost of construction at Old Oak Common Great Western rail station, and (2) the total time for construction from the beginning of works to the opening of the station for passengers.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL581"} , {"_about" : "http://data.parliament.uk/resources/1672976", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672976/answer", "answerText" : {"_value" : "

The whole cost of the new Old Oak Common station is funded through HS2, including the station on the Great Western Main Line.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-06", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-06T15:01:41.71Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Old Oak Common Station: Finance"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government whether the funding for Old Oak Common Great Western rail station comes from HS2 Ltd or Network Rail.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL582"} , {"_about" : "http://data.parliament.uk/resources/1672977", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672977/answer", "answerText" : {"_value" : "

Construction of the Old Oak Common conventional station will involve a number of partial and complete closures of the Great Western Main Line east of Ealing Broadway during the period up to 2030 which will impact passenger services and freight operations. My department is working with Network Rail, HS2 Ltd and the train operating companies to minimise the impacts of disruption, combining timing of works with other works planned on the route wherever possible, and ensure the continued operation of rail services.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-06", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-06T15:01:24.51Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Old Oak Common Station: Construction"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government over what time periods rail services to and from Paddington Station will be disrupted due to construction for Old Oak Common Great Western station; and what alternative arrangements will be made for passengers.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL583"} , {"_about" : "http://data.parliament.uk/resources/1672978", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1672978/answer", "answerText" : {"_value" : "

The current assumption is that all passenger trains on the Great Western Mainline will stop at the new Old Oak Common station. Current estimates indicate stopping trains at this station is likely to add approximately 3 minutes, though this would be dependent on further timetable analysis.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4499", "label" : {"_value" : "Biography information for Lord Davies of Gower"} } , "answeringMemberPrinted" : {"_value" : "Lord Davies of Gower"} , "dateOfAnswer" : {"_value" : "2023-12-06", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-12-06T15:07:27.003Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Old Oak Common Station"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask His Majesty's Government what proportion of intercity trains are planned to stop at Old Oak Common Great Western rail station when it is fully operational; and what is the additional journey time between Reading and London for trains that will call at Old Oak Common.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3526", "label" : {"_value" : "Biography information for Lord Berkeley"} } , "tablingMemberPrinted" : [{"_value" : "Lord Berkeley"} ], "uin" : "HL584"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 6, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }