question text To ask the Secretary of State for Defence, with reference to the Answer of 15 December 2015 to Question 20228 on AWE, what his most recent estimate is of the (a) anticipated out-turn cost and (b) projected in-service date of each of the new build projects in the Atomic Weapons Establishment Site Development Context Plan. more like this
tabling member constituency Oxford East more like this
tabling member printed
Anneliese Dodds more like this
uin 198373 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2018-12-06more like thismore than 2018-12-06
answer text <p>The tables below show the approved costs and in-service dates of the new build projects listed in the Atomic Weapons Establishment Site Development Context Plan (SDCP).</p><p> </p><p>In-service dates are shown in bandings to avoid prejudice to national security and defence. Costs for planned projects are subject to approval.</p><p> </p><p>Table 1 – Approved new build projects.</p><p> </p><table><tbody><tr><td><p><strong><em>Ongoing projects</em></strong></p></td><td><p><strong>Function</strong></p></td><td><p><strong>In-Service Period</strong></p></td><td><p><strong>Approved cost</strong></p></td></tr><tr><td><p>Warhead assembly/disassembly – Mensa</p></td><td><p>Manufacturing/ production</p></td><td><p>2023</p></td><td><p>£1.8 billion</p></td></tr><tr><td><p>Uranium components – Pegasus</p></td><td><p>Manufacturing/ production</p></td><td><p>Requirement under consideration</p></td><td><p>£634 million</p></td></tr></tbody></table><p> </p><p> </p><p> </p><p> </p><p> </p><p> </p><p>Table 2 – Planned projects not yet approved.</p><p> </p><table><tbody><tr><td><p><strong><em>Ongoing projects</em></strong></p></td><td><p><strong>Function</strong></p></td><td><p><strong>In-Service Period</strong></p></td></tr><tr><td><p>Salts Processing - Octans</p></td><td><p>Testing/research</p></td><td><p>2020-25</p></td></tr><tr><td><p>Initiator system manufacture-Taurus</p></td><td><p>Manufacturing/production</p></td><td><p>2025-30</p></td></tr><tr><td><p>Large Scale formulations-Scorpius</p></td><td><p>Manufacturing/production</p></td><td><p>2030-40</p></td></tr><tr><td><p>Depleted Uranium Facility</p></td><td><p>Manufacturing/production</p></td><td><p>2020-25</p></td></tr><tr><td><p>Assembly for Trials-Columba</p></td><td><p>Testing/research</p></td><td><p>2030-35</p></td></tr><tr><td><p>High Explosive Climatic Trials</p></td><td><p>Testing/research</p></td><td><p>2030-35</p></td></tr></tbody></table><p> </p><p>Four of the projects previously listed are no longer included, as it is now planned to use the existing facilities. These are Small Scale Formulations (Cepheus), New Plutonium Facility, Non-Metallics and Materials (Libra) and Chemical Processing (Astra).</p><p>Planned new build projects now also include the Hub, a testing/research facility to be brought into service over the period 2020 – 2025.</p><p> </p>
answering member constituency Pudsey more like this
answering member printed Stuart Andrew more like this
question first answered
less than 2018-12-06T17:12:47.5Zmore like thismore than 2018-12-06T17:12:47.5Z
answering member
4032
label Biography information for Stuart Andrew more like this
tabling member
4657
label Biography information for Anneliese Dodds remove filter