answer text |
<p>This incident has been investigated and the Contractor, GEOAmey, has accepted they
failed to deliver one of the defendants by the time ordered by the Judge. The Judge’s
Order was overlooked and instead arrangements were made to deliver that particular
defendant to court at the time usually expected under the Contract, based on the distance
from the prison where they were held to the court. The other two defendants were delivered
to court on time in line with contractual arrangements.</p><p> </p><p>Liquidated damages
are a standard tariff applied to all contractors as a genuine pre-estimate of probable
loss based on the cost of delay to the court and which are applied incrementally according
to the amount of time delayed. The liquidated damages incurred for the delay to Plymouth
Crown Court on 28 October are £2,094.75 and will be paid by GEOAmey as required under
the Contract.</p>
|
|