<p>The current lane closures are scheduled to be lifted in early February this year.
These will be followed by further lane closures on the eastbound carriageway until
early March 2019.</p><p> </p><p>The lane closures are in place as Highways England
are replacing the safety barrier at various sites along this section of the M180.</p><p>
</p><p>Highways England have removed the existing safety barriers, and have erected
temporary barriers in place to protect the now exposed structures. Lane closures must
remain on a 24-hour basis because it would be unsafe for Highways England to remove
the temporary barriers while works continue.</p><p> </p><p>These closures are necessary
to cover various work locations and enable more activity to take place across the
whole site, so as to minimise the programme’s total duration and therefore reduce
the overall disruption. Work takes place throughout the day; the overnight closures
also allow for the concrete used on the foundations and ends of the new barriers to
set.</p>
|
|