1543746
registered interest false more like this
date less than 2022-11-18more like thismore than 2022-11-18
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy more like this
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Nuclear Power Stations remove filter
house id 2 remove filter
legislature
25277
pref label House of Lords more like this
question text To ask His Majesty's Government when they expect new nuclear power generating capacity to come online in the UK. more like this
tabling member printed
Baroness Kennedy of Cradley more like this
uin HL3554 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2022-12-02more like thismore than 2022-12-02
answer text <p>The target date for commercial operations of reactor 1 at Hinkley Point C (HPC) is 1 June 2027. In order to achieve the up to 24GW deployment pathway by 2050, as set out in the British Energy Security Strategy, the Government intends to take one project to Final Investment Decision (FID) this Parliament and two projects to FID in the next Parliament, including Small Modular Reactors.</p><p> </p><p>The Government is in constructive, ongoing negotiations on the Sizewell C project, which would be a replica of HPC. As announced in the Autumn Statement, subject to final approvals, the Government intends to support further development of the project, with an investment of £700m.</p> more like this
answering member printed Lord Callanan more like this
question first answered
less than 2022-12-02T14:14:39.713Zmore like thismore than 2022-12-02T14:14:39.713Z
answering member
4336
label Biography information for Lord Callanan more like this
tabling member
4303
label Biography information for Baroness Kennedy of Cradley more like this