Linked Data API

Show Search Form

Search Results

748338
registered interest false more like this
date remove filter
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy more like this
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Electricity Interconnectors remove filter
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Business, Energy and Industrial Strategy, what operational interconnectors there are in the UK; and what the MW capacity is of each of those interconnectors. more like this
tabling member constituency Stone more like this
tabling member printed
Sir William Cash more like this
uin 2896 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-07-12more like thismore than 2017-07-12
answer text <p>The UK currently has 4GW (4000MW) of operational interconnection capacity:</p><p> </p><ul><li>IFA (Interconnexion France-Angleterre); 2GW (2000MW) from Folkestone, Kent to Calais, France, operating since 1986;</li><li>Moyle; 500MW between South Ayrshire, Scotland and County Antrim, Northern Ireland, operating since 2002;</li><li>Britned; 1GW (1000MW) from the Isle of Grain, Kent, to Rotterdam in the Netherlands, operating since 2011;</li><li>East-West (EWIC); 500MW connecting Barkby Beach, North Wales to Dublin, Ireland, operating since 2012.</li></ul><p> </p> more like this
answering member constituency Watford more like this
answering member printed Richard Harrington more like this
question first answered
less than 2017-07-12T10:42:46.217Zmore like thismore than 2017-07-12T10:42:46.217Z
answering member
4068
label Biography information for Lord Harrington of Watford more like this
tabling member
288
label Biography information for Sir William Cash more like this
748343
registered interest false more like this
date remove filter
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy more like this
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Electricity Interconnectors remove filter
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Business, Energy and Industrial Strategy, how many megawatts of new interconnector capacity are proposed by (a) 2020 and (b) 2025. more like this
tabling member constituency Stone more like this
tabling member printed
Sir William Cash more like this
uin 2897 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-07-12more like thismore than 2017-07-12
answer text <p>The UK has a pipeline of interconnector projects that are expected to play a role in providing reliable, affordable, and clean energy.</p><p> </p><p>Based on current project timelines and assuming all projects are able to complete, 3GW (3000MW) of new interconnector capacity are expected to be operational by 2020. A further 1.4GW is also currently under construction for delivery after 2020. There are a further 9.5GW of projects which have sought regulatory approval.</p><p> </p> more like this
answering member constituency Watford more like this
answering member printed Richard Harrington more like this
question first answered
less than 2017-07-12T10:27:54.83Zmore like thismore than 2017-07-12T10:27:54.83Z
answering member
4068
label Biography information for Lord Harrington of Watford more like this
tabling member
288
label Biography information for Sir William Cash more like this
748344
registered interest false more like this
date remove filter
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy more like this
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Electricity Interconnectors remove filter
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Business, Energy and Industrial Strategy, what proportion of electricity will be supplied by interconnectors in (a) 2020 and (b) 2025. more like this
tabling member constituency Stone more like this
tabling member printed
Sir William Cash more like this
uin 2898 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-07-11more like thismore than 2017-07-11
answer text <p>The proportion of electricity that will be supplied by electricity imports by 2020 is expected to be 7.6%.</p><p> </p><p>The power supply sector is projected using the reference case scenario from the Energy and Emissions Projections 2016 (published March 2017), which can be found here: <a href="https://www.gov.uk/government/publications/updated-energy-and-emissions-projections-2016" target="_blank">https://www.gov.uk/government/publications/updated-energy-and-emissions-projections-2016</a></p><p> </p><p>Up to 2020, the reference scenario reflects current power sector policies. Beyond 2020, the reference scenario includes assumptions that go beyond current Government policy. The results do not indicate a preferred outcome and should be treated as illustrative.</p><p> </p><p><strong> </strong></p> more like this
answering member constituency Watford more like this
answering member printed Richard Harrington more like this
question first answered
less than 2017-07-11T14:44:28.4Zmore like thismore than 2017-07-11T14:44:28.4Z
answering member
4068
label Biography information for Lord Harrington of Watford more like this
tabling member
288
label Biography information for Sir William Cash more like this