1653489
registered interest false more like this
date less than 2023-07-17more like thismore than 2023-07-17
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading Fleet Solid Support Ships: Procurement more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Defence, what his Departments planned timescale for the design and construction of the Fleet Solid Support Ships beginning with the awarding of the contract to the Team Resolute consortium in November 2022. more like this
tabling member constituency Birkenhead more like this
tabling member printed
Mick Whitley more like this
uin 194575 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2023-07-20more like thismore than 2023-07-20
answer text <p>On current plans, construction of the Fleet Solid Support ships will begin in 2025 with the first ship expected to enter service in 2031, and all three ships in operational service by 2032, which will deliver the Full Operating Capability for the Fleet Solid Support programme.</p> more like this
answering member constituency South Suffolk more like this
answering member printed James Cartlidge more like this
question first answered
less than 2023-07-20T09:54:45.037Zmore like thismore than 2023-07-20T09:54:45.037Z
answering member
4519
label Biography information for James Cartlidge more like this
tabling member
4755
label Biography information for Mick Whitley more like this