678248
registered interest false more like this
date less than 2017-01-24more like thismore than 2017-01-24
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy remove filter
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Tidal Power: Swansea Bay more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty’s Government what volume of electricity a Swansea tidal lagoon would produce per annum and at what cost per MWh; and what would be its contribution towards security of supply during the morning and evening peak demand periods. more like this
tabling member printed
Lord Stoddart of Swindon more like this
uin HL4977 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-02-06more like thismore than 2017-02-06
answer text <p>If built, the tidal lagoon at Swansea Bay is anticipated to generate approximately 0.5 TWh/year. The levelised cost of the project (in MWh) would depend on a number of factors including the capital costs, operating costs, operating profile, load factor and financing rates. For reasons of commercial sensitivity I cannot comment on the specifics of the developer’s latest proposal. Its contribution to security of supply would be subject to a number of factors including the state of the tides.</p> more like this
answering member printed Lord Prior of Brampton more like this
question first answered
less than 2017-02-06T15:19:20.05Zmore like thismore than 2017-02-06T15:19:20.05Z
answering member
127
label Biography information for Lord Prior of Brampton remove filter
tabling member
950
label Biography information for Lord Stoddart of Swindon more like this