<p>Recognising the challenging economic backdrop environment, we continue to work
with local areas to find practical solutions to project delivery issues. We are working
with projects to make sensible adjustments to the scope and phasing of their Levelling
Up Fund (LUF) projects where necessary to mitigate delivery challenges whilst maintaining
value for money. To date the Levelling Up Fund has received 61 project adjustment
requests – 37 have been approved, 1 has been rejected, 16 were withdrawn, and a further