hansard heading Warships: River Clyde more like this
house id 2 remove filter
legislature
25277
pref label House of Lords more like this
question text To ask His Majesty's Government what steps they will take to ensure that the five new warships to be built on the Clyde are not subject to delay. more like this
tabling member printed
Lord Berkeley more like this
uin HL3406 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2022-11-29more like thismore than 2022-11-29
answer text <p>The Type 26 Batch 2 contract is structured to motivate both the Ministry of Defence and BAE Systems to deliver a successful outcome, with both parties sharing in the pain and gain in delivering the programme, ensuring value for public money and protecting the taxpayers from any project overrun costs.</p><p>The Batch 2 contract introduces further investment in BAE Systems' shipbuilding facilities on the Clyde, as demonstrated by the submission of planning application for a new Shipbuilding Hall at Govan, which will allow two frigates to be built under cover simultaneously and enable the ships to be built faster, improving the efficiency in the programme and expanding the facilities for future work at the yard.</p> more like this
answering member printed Baroness Goldie more like this
question first answered
less than 2022-11-29T15:01:47.987Zmore like thismore than 2022-11-29T15:01:47.987Z
answering member
4306
label Biography information for Baroness Goldie more like this
tabling member
3526
label Biography information for Lord Berkeley more like this