1147422
registered interest false more like this
date less than 2019-10-01more like thismore than 2019-10-01
answering body
Department for Business, Energy and Industrial Strategy more like this
answering dept id 201 more like this
answering dept short name Business, Energy and Industrial Strategy more like this
answering dept sort name Business, Energy and Industrial Strategy more like this
hansard heading Hinkley Point C Power Station more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised commissioning date is for Hinkley Point C nuclear power station; and if she will make a statement. more like this
tabling member constituency Kilmarnock and Loudoun more like this
tabling member printed
Alan Brown more like this
uin 292948 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2019-10-07more like thismore than 2019-10-07
answer text <p>EDF is the lead investor in Hinkley Point C and, together with its investment partners, is responsible for the project’s schedule. On 25 September 2019, EDF confirmed the project’s intent to generate power from Unit 1 at the end of 2025, which has not changed from the date previously stated on 3 July 2017.</p> more like this
answering member constituency Stratford-on-Avon remove filter
answering member printed Nadhim Zahawi more like this
question first answered
less than 2019-10-07T13:18:06.37Zmore like thismore than 2019-10-07T13:18:06.37Z
answering member
4113
label Biography information for Nadhim Zahawi more like this
tabling member
4470
label Biography information for Alan Brown more like this