<p>In Highways England’s Delivery Plan for roads period 2015-2020 the M60 Junction
8 to M62 Junction 20 Smart Motorway Scheme was forecast to be open to traffic in quarter
2 of the 2017/18 financial year. In August 2017, Highways England published their
Delivery Plan Update (Supplementary Annex) and the construction programme for this
scheme was extended so that additional works including flood mitigation and pavement
resurfacing could be completed under the existing restrictions. This will help avoid
the need for future additional network access in this location. Highways England is
opening the scheme in phases. Junction 18 – 20 of the M62 and Junction 8 – 10 of the
M60 are now open. Full completion is expected by the end of summer 2018.</p>
|
|