hansard heading Hinkley Point C Power Station more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Business, Energy and Industrial Strategy, when his Department plans to make a decision on the timetable for the construction of Hinkley Point C. more like this
tabling member constituency Sunderland Central remove filter
tabling member printed
Julie Elliott more like this
uin 48528 more like this
answer
answer
is ministerial correction false more like this
date of answer remove filter
answer text <p>The construction timetable of the Hinkley Point C power plant is a matter for the developer. The Contract for Difference includes a target commissioning date of 01/05/2025 for reactor 1 and 01/11/2025 for reactor 2.</p><p> </p> more like this
answering member constituency Hereford and South Herefordshire remove filter
answering member printed Jesse Norman more like this
question first answered
less than 2016-10-19T15:48:09.493Zmore like thismore than 2016-10-19T15:48:09.493Z
answering member
3991
label Biography information for Jesse Norman more like this
tabling member
4127
label Biography information for Julie Elliott more like this