<p>The Single Living Accommodation Modernisation (SLAM) Programme is complete.</p><p>
</p><p>The SLAM Programme was a 10 year contract awarded by the Ministry of Defence
in 2002. In late 2012, during the last six months of the contract, 14 new build projects
were added. Design and construction of these projects followed with completion in
2016. The Final Account of the SLAM Programme took place in 2017.</p><p> </p><p>The
SLAM Programme was one of the largest new build and refurbishment programmes in the
UK and delivered successful renovations and constructions on 52 locations from Scotland
to Cornwall. 121 separate projects improved or created more than 22,000 bedspaces.</p>
|