hansard heading Midland Main Line: Electrification more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what his Department's planned timeframe is for electrifying the Midland mainline to Sheffield. more like this
tabling member constituency Barnsley Central more like this
tabling member printed
Dan Jarvis remove filter
uin 166237 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2023-03-20more like thismore than 2023-03-20
answer text <p>The next phase of MML electrification is already underway with overhead line equipment being installed between Kettering and Wigston.</p><p> </p><p>We continue the development of HS2 East, for which MML electrification is essential. We intend to publish the RNEP shortly which will confirm the latest position on all Network Rail schemes including electrification of the MML to Sheffield and Nottingham.</p><p><strong> </strong></p> more like this
answering member constituency Bexhill and Battle more like this
answering member printed Huw Merriman more like this
question first answered
less than 2023-03-20T14:31:50.917Zmore like thismore than 2023-03-20T14:31:50.917Z
answering member
4442
label Biography information for Huw Merriman more like this
tabling member
4243
label Biography information for Dan Jarvis more like this