Linked Data API

Show Search Form

Search Results

44133
registered interest false more like this
date less than 2014-03-19more like thismore than 2014-03-19
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what evaluation his Department has made of the costs and benefits of linking the proposed phase two of High Speed 2 to the West Coast Main Line at Crewe instead of at Golborne junction. more like this
tabling member constituency Altrincham and Sale West more like this
tabling member printed
Mr Graham Brady more like this
uin 192911 remove filter
answer
answer
is ministerial correction false more like this
date of answer less than 2014-03-24more like thismore than 2014-03-24
answer text The Strategic Case for HS2 published on 29 October 2013 sets out the business case for proceeding with HS2. It shows that the Y-shaped network including the connections to the West Coast Main Line at both Crewe and Golborne is expected to deliver around £2.30 of benefits (including Wider Economic Impacts) for every £1 spent. The Department has not estimated the case for the Y-shaped route for High Speed 2 without these connections. However, HS2 Ltd examined the possibility of only linking High Speed 2 to the West Coast Main Line at Crewe, and eliminating the junction at Golborne. They identified significant constraints in the West Coast Main Line north of Crewe and additional works would be required here as the line is intensively used by fast long-distance services, slower stopping trains and freight, causing significant timetabling constraints. Taking into account the levels of growth being experienced to date, both in terms of passenger and freight traffic, the West Coast Main Line would not be able to cope with the overall volume of services required. Therefore the section of line between Winterbottom and Bamfurlong culminating in the Golborne connection is likely to offer very high value for money when compared against the alternative connection at Crewe and associated WCML modification work.
answering member constituency Scarborough and Whitby more like this
answering member printed Mr Robert Goodwill more like this
question first answered
less than 2014-03-24T12:00:00.00Zmore like thismore than 2014-03-24T12:00:00.00Z
answering member
1562
label Biography information for Sir Robert Goodwill more like this
tabling member
435
label Biography information for Sir Graham Brady more like this