Linked Data API

Show Search Form

Search Results

1176850
registered interest false more like this
date less than 2020-02-06more like thismore than 2020-02-06
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading A47 more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what the planned dates for start of (a) construction and (b) completion were for each of the six A47 improvement schemes under the Roads Investment Strategy at the time that strategy was published; and what the status is of each of those schemes. more like this
tabling member constituency North West Norfolk remove filter
tabling member printed
James Wild more like this
uin 13604 remove filter
answer
answer
is ministerial correction false more like this
date of answer less than 2020-02-11more like thismore than 2020-02-11
answer text <p>As part of the first Roads Investment Strategy, the six A47 improvement schemes were due to start construction in 2019/20. In 2017 we announced that some adjustments were made to the sequencing of scheme delivery across the Road Investment Strategy programme, which moved five of the six A47 schemes into the second Road Investment Strategy period which will run from 2020 to 2025. The A47 schemes represent the biggest one-time investment in the A47.</p><p> </p><p>The sixth scheme is the A47 Great Yarmouth Junctions. The scope of the A47 Great Yarmouth Junctions scheme is under review in light of the new Great Yarmouth third river crossing. Originally, this proposed to improve the Vauxhall and Gapton roundabouts in Great Yarmouth; but the effects of the new crossing mean that these improvements no longer match the expected pattern of traffic. The scheme will be redesigned to take new circumstances into account and the junctions will be delivered once the crossing is in place. The Government is committed to tackling road congestion in Great Yarmouth.</p><p> </p><p>The six A47 schemes are currently scheduled for a phased start of works, with the first construction starting in 2021. This has been done to smooth the timing and frequency of the roadworks along the A47, reducing the impact on the public. Specific timescales will be confirmed following publication of the second Roads Investment Strategy shortly.</p><p> </p>
answering member constituency Daventry more like this
answering member printed Chris Heaton-Harris more like this
question first answered
less than 2020-02-11T16:51:50.973Zmore like thismore than 2020-02-11T16:51:50.973Z
answering member
3977
label Biography information for Chris Heaton-Harris more like this
tabling member
4787
label Biography information for James Wild more like this