<p>Expenditure for the Manufacture phases for the Type 26 and Type 31 frigate programmes
(rounded to the nearest million) is detailed in the table below. Costs incurred against
the Assessment Phase have not been included, in line with normal reporting against
Business Case approvals. The costs Spend data for the current financial year (FY2022-23),
is excluded as this is incomplete.</p><p> </p><p> </p><table><tbody><tr><td><p><strong>Project</strong>
<strong>Name</strong></p></td><td><p>FY2017-18 £ million</p></td><td><p>FY2018-19
£ million</p></td><td><p>FY2019-20 £ million</p></td><td><p>FY2020-21 £ million</p></td><td><p>FY2021-22
£ million</p></td></tr><tr><td><p><strong>Type 26</strong></p></td><td><p>288.8</p></td><td><p>464.3</p></td><td><p>507</p></td><td><p>572.3</p></td><td><p>642.2</p></td></tr><tr><td><p><strong>Type
31</strong></p></td><td><p> </p></td><td><p> </p></td><td><p>75.4</p></td><td><p>199.2</p></td><td><p>252.6</p></td></tr></tbody></table><p>
</p>
|
|