hansard heading Carillion: Insolvency more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government what assessment they have made of the impact of the collapse of Carillion Construction Limited on the timetable and budget for HS2 phase one enabling works, design and pre-construction activity. more like this
tabling member printed
Lord Berkeley more like this
uin HL5577 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2018-03-06more like thismore than 2018-03-06
answer text <p>Carillion were not awarded contracts for the Phase One enabling works (termed the Enabling Works Contracts or EWC). Carillion were originally part of the joint venture CEK that was awarded two of the main work civils contracts. These contracts are being taken forward by Kier and Eiffage, the other parties to the CEK joint venture. Each company's Boards have both given that assurance and confirmed that they underwrite the performance of each other and have the capacity to deliver the HS2 contracts under the same terms, including cost and schedule.</p> more like this
answering member printed Baroness Sugg more like this
grouped question UIN HL5578 more like this
question first answered
less than 2018-03-06T12:46:23.6Zmore like thismore than 2018-03-06T12:46:23.6Z
answering member
4584
label Biography information for Baroness Sugg more like this
tabling member
3526
label Biography information for Lord Berkeley more like this