{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&hansardHeading=Electricity+Interconnectors", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&hansardHeading=Electricity+Interconnectors", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&_metadata=all&hansardHeading=Electricity+Interconnectors", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&hansardHeading=Electricity+Interconnectors", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&hansardHeading=Electricity+Interconnectors", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?min-answer.questionFirstAnswered.=2018-03-01T15%3A23%3A16.427Z&hansardHeading=Electricity+Interconnectors", "items" : [{"_about" : "http://data.parliament.uk/resources/1700801", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1700801/answer", "answerText" : {"_value" : "

Government consider that interconnectors will play a key role in enabling greater security of supply by providing access to a more diverse electricity generation mix, responding to shocks in the GB system by importing electricity.<\/p>

<\/p>

The Capacity Market (CM) is our main tool for ensuring security of electricity supply. CM auction targets are set based on advice from the Electricity System Operator\u2019s Electricity Capacity Report which considers the contribution interconnectors make to security of supply.<\/p>

<\/p>

With the exception of 2022, GB has historically been a net importer of electricity, though ESO forecasts suggest that GB will likely become a net exporter in future.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4105", "label" : {"_value" : "Biography information for Justin Tomlinson"} } , "answeringMemberConstituency" : {"_value" : "North Swindon"} , "answeringMemberPrinted" : {"_value" : "Justin Tomlinson"} , "dateOfAnswer" : {"_value" : "2024-04-23", "_datatype" : "dateTime"} , "groupedQuestionUIN" : {"_value" : "21592"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2024-04-23T09:54:49.107Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2024-04-15", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Electricity Interconnectors"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, what assessment she has made of the potential impact of the use of electricity interconnectors on energy (a) security and (b) supply.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1447", "label" : {"_value" : "Biography information for Andrew Rosindell"} } , "tablingMemberConstituency" : {"_value" : "Romford"} , "tablingMemberPrinted" : [{"_value" : "Andrew Rosindell"} ], "uin" : "21587"} , {"_about" : "http://data.parliament.uk/resources/1698435", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1698435/answer", "answerText" : {"_value" : "

As of March 2024, Great Britain has 9.8GW interconnection capacity in operation. A further 1.9 GW of interconnection is in construction, with 0.5GW expected to be operational by 2025. Anticipated interconnection capacity by 2025 is therefore approximately 10.3GW.<\/p>

<\/p>

In 2020, the Government set an ambition to realise at least 18GW of interconnection by 2030; this was reaffirmed in 2023.<\/p>

<\/p>

Two additional interconnectors, totalling 3.2GW, have recently received positive interim regulatory decisions from Ofgem. If progressed, Great Britain will be on track for 13.1GW of interconnection capacity by 2030, and 14.9GW by 2031.<\/p>

<\/p>

The Government will provide more information on interconnection post-2030 in due course.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4105", "label" : {"_value" : "Biography information for Justin Tomlinson"} } , "answeringMemberConstituency" : {"_value" : "North Swindon"} , "answeringMemberPrinted" : {"_value" : "Justin Tomlinson"} , "dateOfAnswer" : {"_value" : "2024-04-17", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2024-04-17T05:35:16.357Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2024-03-25", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Electricity Interconnectors"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, what her Department's policy is on the future capacity of new electricity interconnectors in (a) 2025, (b) 2030 and (c) 2040.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1447", "label" : {"_value" : "Biography information for Andrew Rosindell"} } , "tablingMemberConstituency" : {"_value" : "Romford"} , "tablingMemberPrinted" : [{"_value" : "Andrew Rosindell"} ], "uin" : "20212"} , {"_about" : "http://data.parliament.uk/resources/1698436", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1698436/answer", "answerText" : {"_value" : "

Ofgem is responsible for awarding regulatory approval to electricity interconnector projects in Great Britain. There are two main routes to regulatory approval, through the awarding of a cap and floor regime, or a merchant route. Including both routes, Ofgem has given approval to the following projects:<\/p>