{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptShortName=Transport&dateTabled=2015-06-03&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answeringDeptShortName=Transport&dateTabled=2015-06-03&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptShortName=Transport&dateTabled=2015-06-03&_metadata=all&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptShortName=Transport&_page=0&dateTabled=2015-06-03&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptShortName=Transport&dateTabled=2015-06-03&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptShortName=Transport&dateTabled=2015-06-03&max-questionFirstAnswered.=2015-06-09T12%3A16%3A55.227Z", "items" : [{"_about" : "http://data.parliament.uk/resources/348401", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/348401/answer", "answerText" : {"_value" : "
The Government has made no estimate of the cost of electrifying the Gospel Oak to Barking railway line. Network Rail will provide an estimate following formal sign-off of stage 3 of the Governance for Railway Investment Projects (\u2018GRIP\u2019) process.<\/p>
<\/p>
The Department for Transport has allocated £90 million towards the project (2013 prices).<\/p>
<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3974", "label" : {"_value" : "Biography information for Claire Perry"} } , "answeringMemberConstituency" : {"_value" : "Devizes"} , "answeringMemberPrinted" : {"_value" : "Claire Perry"} , "dateOfAnswer" : {"_value" : "2015-06-08", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2015-06-08T11:04:06.143Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2015-06-03", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Gospel Oak-Barking Railway Line: Electrification"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, what estimate he has made of the cost of electrifying the Gospel Oak to Barking railway line; and what contribution his Department plans to make to that project.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4029", "label" : {"_value" : "Biography information for Lilian Greenwood"} } , "tablingMemberConstituency" : {"_value" : "Nottingham South"} , "tablingMemberPrinted" : [{"_value" : "Lilian Greenwood"} ], "uin" : "966"} , {"_about" : "http://data.parliament.uk/resources/348408", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/348408/answer", "answerText" : {"_value" : "
The Office of Rail and Road (ORR) is responsible for determining the efficient cost of Network Rail\u2019s CP5 enhancement schemes, not the Department for Transport.<\/p>
<\/p>
As explained in my previous response to the Honourable Member for Nottingham South, the ORR publishes quarterly updates on the enhancements cost adjustment mechanism (ECAM) process. This includes information about efficiencies identified on specific schemes through the ECAM process. For example, the ORR recently published ECAM findings on Reading Station area redevelopment, Great Western electrification and Midland Main Line electrification on its website:<\/p>