{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptId=27&_metadata=all&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "items" : [{"_about" : "http://data.parliament.uk/resources/1016337", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016337/answer", "answerText" : {"_value" : "

A geotechnical baseline report (GBR) is a contractual document that defines what the Contractor has to allow for in his price. The actual geotechnical parameters from HS2 project ground investigations have been and are being used for the assessment of \u201call\u201d buildings impacted by the works including potential ground movements associated with excavations and to assess, in the rare event, any necessary remedial measures. For further information for Phases 1 & 2a see HS2 Information Papers C3 & C14 \u2013 Ground Settlement, respectively.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-03", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-03T14:38:49.783Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, whether he has made an assessment of the potential merits of using geotechnical baseline reports to assess the possible (a) settlement damage to and (b) strengthening required for buildings along the High Speed Two London tunnel route.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196819"} , {"_about" : "http://data.parliament.uk/resources/1016344", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016344/answer", "answerText" : {"_value" : "

The nominated undertaker (HS2) will reimburse reasonable costs subject to the conditions outlined in the Information Papers C3 & C14 that were prepared in support of the Phase 1 Act. Please refer to Section 8 of the Information Paper.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-05", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-05T11:35:49.15Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, whether (a) HS2 Ltd, (b) third party contractors or (c) his Department will be liable in the event that settlement damage to vulnerable and listed buildings occurs due to works along the High Speed Two London tunnel route.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196821"} , {"_about" : "http://data.parliament.uk/resources/1016345", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016345/answer", "answerText" : {"_value" : "

The Department has received a small number of representations regarding the assessment of the risks in relation to HS2 Ltd\u2019s development of the design of the HS2 tunnels on the Park Village East retaining wall, which is located on the approach to Euston Station.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-03", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-03T14:56:32.267Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, what representations his Department has received on the risks to buildings along the High Speed Two London tunnel route in the last six months.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196822"} , {"_about" : "http://data.parliament.uk/resources/1016346", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016346/answer", "answerText" : {"_value" : "

The total funding envelope of the High Speed 2 project was set at £55.7bn (2015 prices) as part of the 2015 Spending Review settlement.<\/p>

The total spend to date is £5.5bn (nominal), inclusive of the financial years 2009-10 to 2017-18.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-03", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-03T14:36:53.933Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, what his latest estimate is of the total cost of High Speed Two; and how much of that funding has been spent.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196823"} , {"_about" : "http://data.parliament.uk/resources/1016352", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016352/answer", "answerText" : {"_value" : "

The table below provides information on the total expenditure incurred by the High Speed Rail Group on consultancy in support of the HS2 project.<\/p>

<\/p>

Financial Year<\/p><\/td>

Expenditure<\/p><\/td><\/tr>

2011-12<\/p><\/td>

£2,310<\/p><\/td><\/tr>

2012-13<\/p><\/td>

£4,803,540<\/p><\/td><\/tr>

2013-14<\/p><\/td>

£5,352,792<\/p><\/td><\/tr>

2014-15<\/p><\/td>

£10,563,780<\/p><\/td><\/tr>

2015-16<\/p><\/td>

£12,045,048<\/p><\/td><\/tr>

2016-17<\/p><\/td>

£10,366,823<\/p><\/td><\/tr>

2017-18<\/p><\/td>

£9,999,662<\/p><\/td><\/tr><\/tbody><\/table>


<\/p>

The amount spent on consultancy reflects the need to utilise the best specialist expertise to deliver the Government\u2019s biggest investment in transport infrastructure in generations. All consultancy contracts are competitively tendered to ensure value for money and every effort is made to transfer skills to permanent staff and ensure reduced reliance on external contractors.<\/p>

<\/p>

I am unable to publish a breakdown to your request as this information is commercially sensitive. The Department for Transport has a duty to manage procurements to deliver the best value for the tax payer, and publishing the breakdown requested would be likely to negatively prejudice the effective and efficient outcome of these procurement competitions.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-07", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-07T13:28:52.663Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, how much money his Department has spent on each (a) consultant and (b) consultancy firm to support the HS2 project in each year since 2010-11.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196824"} , {"_about" : "http://data.parliament.uk/resources/1016355", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016355/answer", "answerText" : {"_value" : "

The Nominated Undertaker (i.e. those acting on behalf of the Secretary of State) will engage with property owners as it is in their combined interest that Settlement Surveys are reflective and factual of the property prior to commencement of tunnel works. The survey will be undertaken by a jointly appointed Independent Chartered Building Surveyor at the nominated undertaker\u2019s cost. This approach was adopted on HS1, Crossrail and Thames Tideway and is a common and recognised practice. See Information Papers C3 & C14 Section 7. The Nominated Undertaker will perform relevant conflict of interest assessments at the appropriate time.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-03", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-03T15:53:17.057Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, whether his Department has made an assessment of the risk of conflicts of interest in relation to settlement deed surveys provided by companies contracted to work on the High Speed Two London Tunnel Route.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196825"} , {"_about" : "http://data.parliament.uk/resources/1016356", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016356/answer", "answerText" : {"_value" : "

HS2 Ltd has spent nothing on compensation grouting to date. HS2 Ltd has required the contractors to procure tunnel boring machines that are capable of limiting ground movements.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-05", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-05T13:36:21.743Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, how much HS2 Ltd has spent on compensation grouting in advance of construction work along the High Speed Two London tunnel route.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196826"} , {"_about" : "http://data.parliament.uk/resources/1016365", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1016365/answer", "answerText" : {"_value" : "

The actual geotechnical parameters from HS2 project ground investigations have been and are being used for the assessment of buildings impacted by the works. Geotechnical baseline reports (GBR) are not precluded by target cost contracts however their use is not considered relevant for the assessment of the impact of potential ground movement on buildings or associated compensation.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4460", "label" : {"_value" : "Biography information for Ms Nusrat Ghani"} } , "answeringMemberConstituency" : {"_value" : "Wealden"} , "answeringMemberPrinted" : {"_value" : "Ms Nusrat Ghani"} , "dateOfAnswer" : {"_value" : "2018-12-03", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-12-03T14:53:21.353Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, whether he has had discussions with HS2 Ltd on the use of target cost contracts instead of geotechnical baseline reports; and what assessment he has made of the potential effect on the level of compensation arising from damage to vulnerable buildings along the High Speed Two construction route of excluding the use of those reports.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4518", "label" : {"_value" : "Biography information for Tulip Siddiq"} } , "tablingMemberConstituency" : {"_value" : "Hampstead and Kilburn"} , "tablingMemberPrinted" : [{"_value" : "Tulip Siddiq"} ], "uin" : "196827"} , {"_about" : "http://data.parliament.uk/resources/1011266", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1011266/answer", "answerText" : {"_value" : "

The current HS2 funding envelope is £55.73bn (at 2015 prices), as set out in the 2015 Spending Review settlement. This is split between phases, with Phase One set at £27.18bn and Phase 2a&b at £28.55bn.<\/p>

<\/p>

At the 2013 Spending Review the HS2 funding envelope was at £50.1bn (at 2011 prices). This funding allocation was split as follows: Phase One £21.4bn, Phase 2 £21.2bn and Rolling Stock £7.5bn. Spending Review 2013 was the first time a long term funding envelope was established for the HS2 network.<\/p>

<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-11-28T12:41:05.017Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-20", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government what is their current estimate of the combined cost of phases 1 and 2 of High Speed 2; and what was the estimated cost of phases 1 and 2 in 2010 when the scheme was reviewed.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4586", "label" : {"_value" : "Biography information for Lord Macpherson of Earl's Court"} } , "tablingMemberPrinted" : [{"_value" : "Lord Macpherson of Earl's Court"} ], "uin" : "HL11627"} , {"_about" : "http://data.parliament.uk/resources/1010140", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1010140/answer", "answerText" : {"_value" : "

HS2 Ltd has been set an ambitious target of commencing HS2 Phase One services in 2026.<\/p>

<\/p>

HS2 Ltd are currently working with their contracted suppliers to deliver Phase One. This involves updating and agreeing an assessment of schedule confidence.<\/p>

<\/p>

The Government will make schedule details public as part of the Full Business Case for Phase One due to be published in 2019.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2018-11-28", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2018-11-28T13:56:45.257Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2018-11-19", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government what assessment they have made of the likelihood of the HS2 rail line being delayed by more than one year.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1796", "label" : {"_value" : "Biography information for Lord Taylor of Warwick"} } , "tablingMemberPrinted" : [{"_value" : "Lord Taylor of Warwick"} ], "uin" : "HL11587"} ], "itemsPerPage" : 10, "next" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=1&answeringDeptId=27&hansardHeading=High+Speed+2+Line&max-answer.dateOfAnswer=2018-12-07", "page" : 0, "startIndex" : 1, "totalResults" : 525, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }