{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&max-answer.dateOfAnswer=2023-11-30", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&max-answer.dateOfAnswer=2023-11-30", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&_metadata=all&max-answer.dateOfAnswer=2023-11-30", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&_page=0&max-answer.dateOfAnswer=2023-11-30", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&max-answer.dateOfAnswer=2023-11-30", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.questionFirstAnswered.=2023-11-30T14%3A26%3A03.083Z&min-answer.dateOfAnswer=2020-09-01&max-answer.dateOfAnswer=2023-11-30", "items" : [{"_about" : "http://data.parliament.uk/resources/1673102", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1673102/answer", "answerText" : {"_value" : "
EDF is the lead investor at Hinkley Point C and they have provided a target date for commercial operations for Unit Reactor 1 of June 2027, with Unit Reactor 2 following a year later in June 2028. Both units have a risk of a delay of 15 months. We expect Sizewell C to be generating power from the mid-2030s, subject to ongoing project development and the timing of a Final Investment Decision.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4601", "label" : {"_value" : "Biography information for Andrew Bowie"} } , "answeringMemberConstituency" : {"_value" : "West Aberdeenshire and Kincardine"} , "answeringMemberPrinted" : {"_value" : "Andrew Bowie"} , "dateOfAnswer" : {"_value" : "2023-11-30", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2023-11-30T14:26:03.083Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2023-11-27", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Hinkley Point C Power Station and Sizewell C Power Station"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, what recent estimate her Department has made of when the (a) Hinkley and (b) Sizewell nuclear power plant will be operational.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4981", "label" : {"_value" : "Biography information for Ashley Dalton"} } , "tablingMemberConstituency" : {"_value" : "West Lancashire"} , "tablingMemberPrinted" : [{"_value" : "Ashley Dalton"} ], "uin" : "4020"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 1, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }