{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.groupedQuestionUIN.=232592&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answer.groupedQuestionUIN.=232592&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.groupedQuestionUIN.=232592&_metadata=all&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answer.groupedQuestionUIN.=232592&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.groupedQuestionUIN.=232592&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.groupedQuestionUIN.=232592&max-answer.dateOfAnswer=2019-07-17&max-answer.questionFirstAnswered.=2019-05-13T14%3A56%3A08.697Z", "items" : [{"_about" : "http://data.parliament.uk/resources/1088689", "AnsweringBody" : [{"_value" : "Ministry of Defence"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1088689/answer", "answerText" : {"_value" : "

The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.<\/p>

At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.<\/p>

At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4032", "label" : {"_value" : "Biography information for Stuart Andrew"} } , "answeringMemberConstituency" : {"_value" : "Pudsey"} , "answeringMemberPrinted" : {"_value" : "Stuart Andrew"} , "dateOfAnswer" : {"_value" : "2019-03-21", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "232591"} , {"_value" : "232592"} , {"_value" : "232593"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-03-21T15:28:38.783Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "11"} , "answeringDeptShortName" : {"_value" : "Defence"} , "answeringDeptSortName" : {"_value" : "Defence"} , "date" : {"_value" : "2019-03-14", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "HMS Forth: Costs"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Defence, what estimate he has made of the cost to the public purse of the River Class 2 patrol vessel, HMS Forth (a) at inception and (b) when it was accepted by the Royal Navy.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4402", "label" : {"_value" : "Biography information for Douglas Chapman"} } , "tablingMemberConstituency" : {"_value" : "Dunfermline and West Fife"} , "tablingMemberPrinted" : [{"_value" : "Douglas Chapman"} ], "uin" : "232590"} , {"_about" : "http://data.parliament.uk/resources/1088691", "AnsweringBody" : [{"_value" : "Ministry of Defence"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1088691/answer", "answerText" : {"_value" : "

The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.<\/p>

At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.<\/p>

At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4032", "label" : {"_value" : "Biography information for Stuart Andrew"} } , "answeringMemberConstituency" : {"_value" : "Pudsey"} , "answeringMemberPrinted" : {"_value" : "Stuart Andrew"} , "dateOfAnswer" : {"_value" : "2019-03-21", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "232590"} , {"_value" : "232592"} , {"_value" : "232593"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-03-21T15:28:38.83Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "11"} , "answeringDeptShortName" : {"_value" : "Defence"} , "answeringDeptSortName" : {"_value" : "Defence"} , "date" : {"_value" : "2019-03-14", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "HMS Forth: Construction"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Defence, what the estimated build time was for HMS Forth at inception; and whether that ship was delivered on time.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4402", "label" : {"_value" : "Biography information for Douglas Chapman"} } , "tablingMemberConstituency" : {"_value" : "Dunfermline and West Fife"} , "tablingMemberPrinted" : [{"_value" : "Douglas Chapman"} ], "uin" : "232591"} , {"_about" : "http://data.parliament.uk/resources/1088693", "AnsweringBody" : [{"_value" : "Ministry of Defence"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1088693/answer", "answerText" : {"_value" : "

The firm price contract for three River Class Offshore Patrol Vessels awarded to BAE Systems in August 2014 has a value of £378 million. The contract does not separately identify the cost of each of the three ships. Of the contract value, £30 million is for items including trials, spares, testing and Government Furnished Equipment. The value of the contract remains unchanged.<\/p>

At contract award, the estimated build time of HMS Forth was 31 months. Delivery of the ship, in January 2018, was not in accordance with the planned schedule, owing to delays during construction. The build of HMS Forth was not affected by design, technical or relationship issues.<\/p>

At contract award, the planned contract acceptance date for HMS Forth was May 2017. Contractor sea trials were expected to commence two months before contractual acceptance.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4032", "label" : {"_value" : "Biography information for Stuart Andrew"} } , "answeringMemberConstituency" : {"_value" : "Pudsey"} , "answeringMemberPrinted" : {"_value" : "Stuart Andrew"} , "dateOfAnswer" : {"_value" : "2019-03-21", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "232590"} , {"_value" : "232591"} , {"_value" : "232592"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-03-21T15:28:38.923Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "11"} , "answeringDeptShortName" : {"_value" : "Defence"} , "answeringDeptSortName" : {"_value" : "Defence"} , "date" : {"_value" : "2019-03-14", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "HMS Forth: Construction"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Defence, at inception what the estimated hand over date of HMS Forth was; and when sea trials were expected to commence.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4402", "label" : {"_value" : "Biography information for Douglas Chapman"} } , "tablingMemberConstituency" : {"_value" : "Dunfermline and West Fife"} , "tablingMemberPrinted" : [{"_value" : "Douglas Chapman"} ], "uin" : "232593"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 3, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }