{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&answer.answeringMemberPrinted=Justin+Tomlinson", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&answer.answeringMemberPrinted=Justin+Tomlinson", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&_metadata=all&answer.answeringMemberPrinted=Justin+Tomlinson", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&answer.answeringMemberPrinted=Justin+Tomlinson", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&answer.answeringMemberPrinted=Justin+Tomlinson", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?legislature.prefLabel=House+of+Commons&answer.dateOfAnswer=2024-04-17&answer.answeringMemberPrinted=Justin+Tomlinson", "items" : [{"_about" : "http://data.parliament.uk/resources/1700136", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1700136/answer", "answerText" : {"_value" : "

The response to pollution incidents from offshore hydrocarbon operations is led by Industry and their primary response contractor Oil Spill Response Limited (OSRL). Since the report was published, the Oil Spill Prevention and Response Advisory Group (OSPRAG) cap was developed and been in service since 2011. OSRL have also developed additional higher rated capping devices which have been in service since 2013. OSRL have also extended their response capability to include a base in the Shetland Islands to respond promptly to incidents West of Shetland. This base contains response equipment which has been specially selected for West of Shetland conditions.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4105", "label" : {"_value" : "Biography information for Justin Tomlinson"} } , "answeringMemberConstituency" : {"_value" : "North Swindon"} , "answeringMemberPrinted" : {"_value" : "Justin Tomlinson"} , "dateOfAnswer" : {"_value" : "2024-04-17", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2024-04-17T09:31:00.587Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2024-04-12", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Oil: Pollution"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, with reference to paragraph 22 of the fifth Special Report of the Energy and Climate Change Committee of Session 2010-11 entitled UK Deepwater Drilling: Implications of the Gulf of Mexico Oil Spill: Government Response to the Committee's Second Report of Session 2010\u201311, HC 882, published on 22 March 2011, what recent progress the Government has made on ensuring that oil spill response equipment is designed to take full account of the harsh environment in the West of Shetland.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/146", "label" : {"_value" : "Biography information for Barry Gardiner"} } , "tablingMemberConstituency" : {"_value" : "Brent North"} , "tablingMemberPrinted" : [{"_value" : "Barry Gardiner"} ], "uin" : "20841"} , {"_about" : "http://data.parliament.uk/resources/1698433", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1698433/answer", "answerText" : {"_value" : "

The Electricity System Operator has published its \u201cFinal Transmission Network Use of System (TNUoS) Tariffs for 2023/24\u201d document, which details that interconnectors are exempt from transmission charges, and the average transmission network tariff for generators is £12.45/kW.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4105", "label" : {"_value" : "Biography information for Justin Tomlinson"} } , "answeringMemberConstituency" : {"_value" : "North Swindon"} , "answeringMemberPrinted" : {"_value" : "Justin Tomlinson"} , "dateOfAnswer" : {"_value" : "2024-04-17", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2024-04-17T05:35:38.953Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2024-03-25", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Electricity Generation and Electricity Interconnectors: Costs"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, whether she has made an estimate of the average transmission network costs for (a) inter connectors and (b) domestic generators of electricity in the last 12 months.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1447", "label" : {"_value" : "Biography information for Andrew Rosindell"} } , "tablingMemberConstituency" : {"_value" : "Romford"} , "tablingMemberPrinted" : [{"_value" : "Andrew Rosindell"} ], "uin" : "20211"} , {"_about" : "http://data.parliament.uk/resources/1698435", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1698435/answer", "answerText" : {"_value" : "

As of March 2024, Great Britain has 9.8GW interconnection capacity in operation. A further 1.9 GW of interconnection is in construction, with 0.5GW expected to be operational by 2025. Anticipated interconnection capacity by 2025 is therefore approximately 10.3GW.<\/p>

<\/p>

In 2020, the Government set an ambition to realise at least 18GW of interconnection by 2030; this was reaffirmed in 2023.<\/p>

<\/p>

Two additional interconnectors, totalling 3.2GW, have recently received positive interim regulatory decisions from Ofgem. If progressed, Great Britain will be on track for 13.1GW of interconnection capacity by 2030, and 14.9GW by 2031.<\/p>

<\/p>

The Government will provide more information on interconnection post-2030 in due course.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4105", "label" : {"_value" : "Biography information for Justin Tomlinson"} } , "answeringMemberConstituency" : {"_value" : "North Swindon"} , "answeringMemberPrinted" : {"_value" : "Justin Tomlinson"} , "dateOfAnswer" : {"_value" : "2024-04-17", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2024-04-17T05:35:16.357Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "215"} , "answeringDeptShortName" : {"_value" : "Energy Security and Net Zero"} , "answeringDeptSortName" : {"_value" : "Energy Security and Net Zero"} , "date" : {"_value" : "2024-03-25", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Electricity Interconnectors"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Energy Security and Net Zero, what her Department's policy is on the future capacity of new electricity interconnectors in (a) 2025, (b) 2030 and (c) 2040.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1447", "label" : {"_value" : "Biography information for Andrew Rosindell"} } , "tablingMemberConstituency" : {"_value" : "Romford"} , "tablingMemberPrinted" : [{"_value" : "Andrew Rosindell"} ], "uin" : "20212"} , {"_about" : "http://data.parliament.uk/resources/1698436", "AnsweringBody" : [{"_value" : "Department for Energy Security and Net Zero"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1698436/answer", "answerText" : {"_value" : "

Ofgem is responsible for awarding regulatory approval to electricity interconnector projects in Great Britain. There are two main routes to regulatory approval, through the awarding of a cap and floor regime, or a merchant route. Including both routes, Ofgem has given approval to the following projects:<\/p>