{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-02-09&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&answer.answeringMemberPrinted=Damian+Hinds", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?date=2021-02-09&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&answer.answeringMemberPrinted=Damian+Hinds", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-02-09&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&_metadata=all&answer.answeringMemberPrinted=Damian+Hinds", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-02-09&_page=0&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&answer.answeringMemberPrinted=Damian+Hinds", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-02-09&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&answer.answeringMemberPrinted=Damian+Hinds", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-02-09&min-answer.questionFirstAnswered.=2017-12-05T15%3A25%3A13.62Z&answer.answeringMemberPrinted=Damian+Hinds", "items" : [{"_about" : "http://data.parliament.uk/resources/1285183", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1285183/answer", "answerText" : {"_value" : "

The Sponsor Body is currently finalising the remaining phase 1 expenditure limit, to be agreed by the Commissions of both Houses.<\/p>

The Parliamentary Works Estimates Commission will review the annual estimate in the context of the limit agreed by the Commissions of both Houses. The annual Estimate will be discussed in a public hearing in March 2021. The Estimates Commission will seek the views of the Treasury before laying the Estimate before the House of Commons.<\/p>

Current costs and expenditure are published as Quarterly Reports, available on the Restoration and Renewal website: www.restorationandrenewal.uk/resources/transparency/the-programme.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-02-22", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-02-22T13:46:00.373Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-02-09", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what the costs are for the (a) business planning and (b) other preliminary works for the Restoration and Renewal Programme before the full works programme begins.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4813", "label" : {"_value" : "Biography information for Mr Richard Holden"} } , "tablingMemberConstituency" : {"_value" : "North West Durham"} , "tablingMemberPrinted" : [{"_value" : "Mr Richard Holden"} ], "uin" : "151882"} , {"_about" : "http://data.parliament.uk/resources/1285208", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1285208/answer", "answerText" : {"_value" : "

The Parliamentary Works Sponsor Body is the single client accountable to Parliament and oversees a Delivery Authority which carries out the work.<\/p>

The Sponsor Body was established in shadow form in July 2018 and became a statutory organisation separate from Parliament on 8 April 2020 and has been engaged in a period of recruitment since then. The staffing is a mixture of directly employed staff, contractors and people seconded from the Houses. As of 31 January 2021, there are 15 directly employed staff in the Sponsor Body, mainly at a senior level and the average costs per employee is £103,633, including National Insurance and Pension.<\/p>

The Delivery Authority was set up as a company limited by guarantee on 16 April 2020, and the Sponsor Body is the sole guarantor. The staffing is a mixture of directly employed staff, contractors and people seconded from the Houses. As of 31 January 2021, there are 55 directly employed staff in the Delivery Authority, mainly at a senior level and the average costs per employee is £86,810, including National Insurance and Pension.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-02-22", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-02-22T13:44:29.137Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-02-09", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, how many staff are employed on the Restoration and Renewal programme; and what the average cost, including employer national insurance and pension contributions, is of those members of staff.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4813", "label" : {"_value" : "Biography information for Mr Richard Holden"} } , "tablingMemberConstituency" : {"_value" : "North West Durham"} , "tablingMemberPrinted" : [{"_value" : "Mr Richard Holden"} ], "uin" : "151884"} , {"_about" : "http://data.parliament.uk/resources/1285225", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1285225/answer", "answerText" : {"_value" : "

The Sponsor Body, working closely with the Delivery Authority, has recently carried out a Strategic Review for how the restoration programme should be carried out. The Sponsor Body looked at all viable options as part of the Strategic Review, including consideration of Church House. The Strategic Review will be published in due course.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-02-22", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-02-22T13:48:02.76Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-02-09", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment the body has made of the viability of Church House as a temporary replacement for the Palace of Westminster while it undergoes essential repairs.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4243", "label" : {"_value" : "Biography information for Dan Jarvis"} } , "tablingMemberConstituency" : {"_value" : "Barnsley Central"} , "tablingMemberPrinted" : [{"_value" : "Dan Jarvis"} ], "uin" : "151715"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 3, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }