{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&max-answer.dateOfAnswer=2019-01-29", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&max-answer.dateOfAnswer=2019-01-29", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&_metadata=all&max-answer.dateOfAnswer=2019-01-29", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&_page=0&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&max-answer.dateOfAnswer=2019-01-29", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&max-answer.dateOfAnswer=2019-01-29", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?tablingMember.label=Biography+information+for+Mr+Marcus+Jones&answer.answerText=%3Cp%3EOver+Control+Period+4%2C+the+total+amount+spent+on+enhancements+on+the+railways+in+England+and+Wales%2C+as+set+out+in+Network+Rail%27s+delivery+plan+update%2C+was+%C2%A37.557+billion+%282012%2F13+prices%29.%3C%2Fp%3E%3Cp%3E+%3C%2Fp%3E%3Cp%3EOver+Control+Period+5%2C+it+is+estimated+that+%C2%A311.446+billion.%3C%2Fp%3E&tablingMemberConstituency=Nuneaton®isteredInterest=false&max-answer.dateOfAnswer=2019-01-29", "items" : [{"_about" : "http://data.parliament.uk/resources/58473", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/58473/answer", "answerText" : {"_value" : "

Over Control Period 4, the total amount spent on enhancements on the railways in England and Wales, as set out in Network Rail's delivery plan update, was £7.557 billion (2012/13 prices).<\/p>

<\/p>

Over Control Period 5, it is estimated that £11.446 billion.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/1562", "label" : {"_value" : "Biography information for Sir Robert Goodwill"} } , "answeringMemberConstituency" : {"_value" : "Scarborough and Whitby"} , "answeringMemberPrinted" : {"_value" : "Mr Robert Goodwill"} , "dateOfAnswer" : {"_value" : "2014-06-12", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2014-06-12T14:38:15.741286Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2014-06-05", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Railways"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, how much was spent on improvements to the railways in England and Wales in Control Period 4; and what estimate he has made of how much will be spent in Control Period 5.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4024", "label" : {"_value" : "Biography information for Mr Marcus Jones"} } , "tablingMemberConstituency" : {"_value" : "Nuneaton"} , "tablingMemberPrinted" : [{"_value" : "Mr Marcus Jones"} ], "uin" : "199233"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 1, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }