{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_metadata=all&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "isPartOf" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&answer.answerText=%3Cp%3EThe%20runway%20was%20closed%20as%20planned%20on%2015%20April%202019%20to%20fixed%20wing%20aircraft.%20Rotary%20wing%20operations%20have%20continued,%20while%20fixed%20wing%20aircraft%20are%20now%20operating%20from%20RAF%20Benson.%3C/p%3E%3Cp%3EConstruction%20works%20have%20commenced%20to%20remove%20the%20existing%20runway%20surface%20and%20arrestor%20beds.%20This%20will%20be%20followed%20by%20preparatory%20works%20for%20resurfacing%20the%20runway,%20installation%20of%20new%20arrestor%20beds%20and%20new%20approach%20lighting.%20Works%20will%20continue%20through%20summer%20to%20be%20completed%20in%20late%20October%202019.%3C/p%3E%3Cp%3EThe%20estimated%20capital%20cost%20of%20the%20project%20is%20%C2%A323%20million%20inclusive%20of%20VAT.%20The%20works%20will%20assure%20military%20flying%20operations%20in%20support%20of%20UK%20Defence%20and%20the%20wider%20Government%20at%20RAF%20Northolt%20for%20the%20next%2010%20-%2015%20years.%3C/p%3E&min-answer.questionFirstAnswered.=2019-05-20T16:38:02.36Z&_properties=answer.isMinisterialCorrection,tablingMember.label,answer.dateOfAnswer,answer,answeringDeptSortName&answer.answeringMemberConstituency=Bournemouth%20East&_sort=answer.answeringMemberPrinted&max-answer.questionFirstAnswered.=2019-05-21T13:17:05.177Z&max-answer.dateOfAnswer=2019-05-20", "type" : "http://purl.org/linked-data/api/vocab#ListEndpoint"} , "items" : [{"_about" : "http://data.parliament.uk/resources/1126612", "AnsweringBody" : [{"_value" : "Ministry of Defence"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1126612/answer", "answerText" : {"_value" : "

The runway was closed as planned on 15 April 2019 to fixed wing aircraft. Rotary wing operations have continued, while fixed wing aircraft are now operating from RAF Benson.<\/p>

Construction works have commenced to remove the existing runway surface and arrestor beds. This will be followed by preparatory works for resurfacing the runway, installation of new arrestor beds and new approach lighting. Works will continue through summer to be completed in late October 2019.<\/p>

The estimated capital cost of the project is £23 million inclusive of VAT. The works will assure military flying operations in support of UK Defence and the wider Government at RAF Northolt for the next 10 - 15 years.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/1487", "label" : {"_value" : "Biography information for Mr Tobias Ellwood"} } , "answeringMemberConstituency" : {"_value" : "Bournemouth East"} , "answeringMemberPrinted" : {"_value" : "Mr Tobias Ellwood"} , "dateOfAnswer" : {"_value" : "2019-05-20", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-05-20T16:48:48.167Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "11"} , "answeringDeptShortName" : {"_value" : "Defence"} , "answeringDeptSortName" : {"_value" : "Defence"} , "date" : {"_value" : "2019-05-14", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "RAF Northolt: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Defence, pursuant to the Answer of 12 March 2019 to Question 228557 on RAF Northolt: Repairs and Maintenance, what progress he has made on (a) the runway and (b) associated infrastructure construction works; what estimate his Department has made of the cost of those works; and if he make a statement.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/177", "label" : {"_value" : "Biography information for Gareth Thomas"} } , "tablingMemberConstituency" : {"_value" : "Harrow West"} , "tablingMemberPrinted" : [{"_value" : "Gareth Thomas"} ], "uin" : "254092"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 1, "type" : "http://purl.org/linked-data/api/vocab#Page"} }