{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-03-04&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?date=2021-03-04&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-03-04&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&_metadata=all", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-03-04&_page=0&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-03-04&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?date=2021-03-04&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z", "items" : [{"_about" : "http://data.parliament.uk/resources/1299652", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1299652/answer", "answerText" : {"_value" : "

The Parliamentary Works Sponsor Body has good working relationships with the Infrastructure and Projects Authority (IPA), HM Treasury and the National Audit Office (NAO). As the Sponsor Body transitioned out of Parliament, where it existed in shadow form, to becoming a formal statutory body, advice was sought from the IPA on good practice and lessons learned in areas such as assurance and governance. The relationship with the IPA continues to be positive and the Sponsor Body has recently worked with the IPA to identify independent reviewers for a forthcoming Gateway Review.<\/p>

Productive discussions continue with HM Treasury regarding the Sponsor Body's preparation of the Outline Business Case for the Restoration and Renewal Programme and, under the terms of the Parliamentary Buildings (Restoration and Renewal) Act 2019, HM Treasury also has a role to provide advice to the Parliamentary Works Estimates Commission on the Sponsor Body's Estimate for each financial year prior to that Estimate being laid in the House of Commons.<\/p>

Both the IPA and HM Treasury contributed to the recent Strategic Review via discussions as part of the Review's Challenge Panel.<\/p>

The NAO published a review of the R&R Programme in April 2020, highlighting the vital and urgent need to restore the Houses of Parliament. That report contained a number of helpful recommendations which the Sponsor Body accepted in full. The Sponsor Body welcomes further reviews by the NAO on behalf of Parliament over the coming years to ensure value for money is delivered for the taxpayer. Both the Sponsor Body and Delivery Authority will also continue to work with the NAO to apply lessons learned from NAO reviews of other projects and programmes as well as in relation to the NAO's role as the external auditor for the Sponsor Body and Delivery Authority.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-03-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-03-11T14:48:37.527Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-03-04", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what advice the Sponsor Body has sought from (a) the Infrastructure and Projects Authority, (b) HM Treasury and (c) the National Audit Office on the costs of the Restoration and Renewal Programme and ensuring value for money.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4737", "label" : {"_value" : "Biography information for Dehenna Davison"} } , "tablingMemberConstituency" : {"_value" : "Bishop Auckland"} , "tablingMemberPrinted" : [{"_value" : "Dehenna Davison"} ], "uin" : "163305"} , {"_about" : "http://data.parliament.uk/resources/1299654", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1299654/answer", "answerText" : {"_value" : "

The Sponsor Body is aware of ongoing fire safety works to the Palace of Westminster. The Outline Business Case will take account of completed works, including fire safety works, when proposing cost estimates for the parliamentary building works under the R&R Programme. This will be conditional on further design work and testing.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-03-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-03-11T14:55:01.56Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-03-04", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, whether the Sponsor Body has made an assessment of the potential effect of the completion of ongoing fire safety works on the cost of the restoration and renewal of the Palace of Westminster.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4737", "label" : {"_value" : "Biography information for Dehenna Davison"} } , "tablingMemberConstituency" : {"_value" : "Bishop Auckland"} , "tablingMemberPrinted" : [{"_value" : "Dehenna Davison"} ], "uin" : "163307"} , {"_about" : "http://data.parliament.uk/resources/1299890", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1299890/answer", "answerText" : {"_value" : "

The Strategic Review report, which is now available on the Restoration and Renewal Programme website, includes a detailed summary of the submissions made by Members of both Houses and by others.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/2542", "label" : {"_value" : "Biography information for Baroness Scott of Needham Market"} } , "answeringMemberPrinted" : {"_value" : "Baroness Scott of Needham Market"} , "dateOfAnswer" : {"_value" : "2021-03-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-03-11T15:08:20.327Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2021-03-04", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask the Parliamentary Works Sponsor Body (1) what plans they have to publish all submissions to the review of the Restoration and Renewal Programme received from Members of both Houses of Parliament and those outside Parliament, (2) if they have such plans, when they will publish those submissions, and (3) if they have no such plans, why not.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4196", "label" : {"_value" : "Biography information for Lord Sharkey"} } , "tablingMemberPrinted" : [{"_value" : "Lord Sharkey"} ], "uin" : "HL13939"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 3, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }