{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&answer.answeringMemberPrinted=Damian+Hinds", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&answer.answeringMemberPrinted=Damian+Hinds", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&_metadata=all&answer.answeringMemberPrinted=Damian+Hinds", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&answer.answeringMemberPrinted=Damian+Hinds", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&answer.answeringMemberPrinted=Damian+Hinds", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?AnsweringBody.=Parliamentary+Works+Sponsor+Body&min-answer.questionFirstAnswered.=2017-12-05T15%3A21%3A08.787Z&max-date=2020-12-10&answer.answeringMemberPrinted=Damian+Hinds", "items" : [{"_about" : "http://data.parliament.uk/resources/1260359", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1260359/answer", "answerText" : {"_value" : "

The Restoration and Renewal Programme is currently creating its business case. Part of this work, once the preferred option has been agreed, will be an environmental assessment on both the construction phase and operations of the restored buildings, where impacts will be assessed and mitigations proposed. To date, no specific conversations have been held on congestion, as the business case work is still in its early stages. The Programme is committed to sustainability and to meeting its environmental obligations.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-01-27", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-01-27T10:15:17.85Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-12-10", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what discussions he has had with (a) Ministers and the (b) House of Commons Commission on the effect of the parliamentary restoration and renewal project on congestion in London.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/411", "label" : {"_value" : "Biography information for Mr Barry Sheerman"} } , "tablingMemberConstituency" : {"_value" : "Huddersfield"} , "tablingMemberPrinted" : [{"_value" : "Mr Barry Sheerman"} ], "uin" : "128054"} , {"_about" : "http://data.parliament.uk/resources/1260360", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1260360/answer", "answerText" : {"_value" : "

The Restoration and Renewal Programme is currently creating its business case. Part of this work, once the preferred option has been agreed, will be an environmental assessment on both the construction phase and operations of the restored buildings, where impacts will be assessed and mitigations proposed. The Programme is committed to sustainability and to meeting its environmental obligations.<\/strong><\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2021-01-27", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2021-01-27T10:12:11.33Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-12-10", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what steps he is taking to mitigate the effect of the parliamentary restoration and renewal project on roadside air pollution in London.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/411", "label" : {"_value" : "Biography information for Mr Barry Sheerman"} } , "tablingMemberConstituency" : {"_value" : "Huddersfield"} , "tablingMemberPrinted" : [{"_value" : "Mr Barry Sheerman"} ], "uin" : "128055"} , {"_about" : "http://data.parliament.uk/resources/1251358", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1251358/answer", "answerText" : {"_value" : "

An initial desk-based assessment of existing data regarding air quality in the vicinity of the Palace of Westminster has been conducted as part of the Restoration and Renewal Programme, and a further assessment will be conducted to provide more accurate and up to date data. These assessments will inform the development of the designs and business case for the restoration works.<\/p>

The Sponsor Body has agreed a strategic objective to mitigate the environmental impact of the Programme during the construction phase and to minimise the impact in relation to the Palace's future operation, in line with its statutory obligations. This objective has been endorsed by the Commissions of both Houses and will be kept under review as the Programme progresses.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-11-19", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-11-19T17:16:34.573Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-11-12", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment of air quality has been made as part of the plans for refurbishing the Palace of Westminster.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/155", "label" : {"_value" : "Biography information for Geraint Davies"} } , "tablingMemberConstituency" : {"_value" : "Swansea West"} , "tablingMemberPrinted" : [{"_value" : "Geraint Davies"} ], "uin" : "114768"} , {"_about" : "http://data.parliament.uk/resources/1201145", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1201145/answer", "answerText" : {"_value" : "

On 19 May the Sponsor Body announced it would conduct a strategic review of the Restoration and Renewal Programme.<\/p>

The review team will be led by the chief executives of the Sponsor Body and Delivery Authority, Sarah Johnson and David Goldstone, who will be supported by infrastructure and programme management experts drawn from both organisations. The chairs of the Sponsor Body and Delivery Authority, Liz Peace and Mike Brown, will also provide input.<\/p>

As the review progresses input and challenge will be sought from within Parliament and externally.<\/p>

The review is expected to conclude in the autumn and its findings will be considered by the Sponsor Body Board and the Commissions of both Houses in the first instance.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-06-16", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-06-16T16:44:23.657Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-06-08", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Right hon. Member for East Hampshire representing the Parliamentary Works Sponsor Body, with reference to the Houses of Parliament Restoration and Renewal press release published on 19 May 2020, what the names are of the people appointed to the expert team to examine the plans for the restoration.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/345", "label" : {"_value" : "Biography information for Sir Edward Leigh"} } , "tablingMemberConstituency" : {"_value" : "Gainsborough"} , "tablingMemberPrinted" : [{"_value" : "Sir Edward Leigh"} ], "uin" : "55862"} , {"_about" : "http://data.parliament.uk/resources/1196531", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1196531/answer", "answerText" : {"_value" : "

The Sponsor Body has agreed a strategic objective to mitigate the environmental impact of the Restoration and Renewal Programme during the construction phase and to minimise the impact in relation to the Palace's future operation. This objective has been endorsed by the Commissions of both Houses and will be kept under review as the Programme progresses. An Environment Impact Assessment will be conducted in due course once the preferred approach to the works has been determined as part of the business case process, which will consider the impact on air quality and river ecology. The Programme is also expected to agree a series of controls and mitigations, as well as monitoring arrangements, for air quality during the construction phase as part of the planning process. The merits of using the river for moving materials to and from the construction site, to minimise the effects of construction on road traffic emissions, will also be considered by the Programme.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-05-22", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "48279"} , {"_value" : "48280"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-05-22T13:02:09.277Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-05-18", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Freight"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what assessment he has made of the potential merits of moving freight to and from the Restoration and Renewal construction site at the Palace of Westminster by river.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/411", "label" : {"_value" : "Biography information for Mr Barry Sheerman"} } , "tablingMemberConstituency" : {"_value" : "Huddersfield"} , "tablingMemberPrinted" : [{"_value" : "Mr Barry Sheerman"} ], "uin" : "48275"} , {"_about" : "http://data.parliament.uk/resources/1196535", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1196535/answer", "answerText" : {"_value" : "

The Sponsor Body has agreed a strategic objective to mitigate the environmental impact of the Restoration and Renewal Programme during the construction phase and to minimise the impact in relation to the Palace's future operation. This objective has been endorsed by the Commissions of both Houses and will be kept under review as the Programme progresses. An Environment Impact Assessment will be conducted in due course once the preferred approach to the works has been determined as part of the business case process, which will consider the impact on air quality and river ecology. The Programme is also expected to agree a series of controls and mitigations, as well as monitoring arrangements, for air quality during the construction phase as part of the planning process. The merits of using the river for moving materials to and from the construction site, to minimise the effects of construction on road traffic emissions, will also be considered by the Programme.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-05-22", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "48275"} , {"_value" : "48280"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-05-22T13:02:09.323Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-05-18", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, whether an environmental impact assessment has been carried out for the Restoration and Renewal project on the Palace of Westminster.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/411", "label" : {"_value" : "Biography information for Mr Barry Sheerman"} } , "tablingMemberConstituency" : {"_value" : "Huddersfield"} , "tablingMemberPrinted" : [{"_value" : "Mr Barry Sheerman"} ], "uin" : "48279"} , {"_about" : "http://data.parliament.uk/resources/1196536", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1196536/answer", "answerText" : {"_value" : "

The Sponsor Body has agreed a strategic objective to mitigate the environmental impact of the Restoration and Renewal Programme during the construction phase and to minimise the impact in relation to the Palace's future operation. This objective has been endorsed by the Commissions of both Houses and will be kept under review as the Programme progresses. An Environment Impact Assessment will be conducted in due course once the preferred approach to the works has been determined as part of the business case process, which will consider the impact on air quality and river ecology. The Programme is also expected to agree a series of controls and mitigations, as well as monitoring arrangements, for air quality during the construction phase as part of the planning process. The merits of using the river for moving materials to and from the construction site, to minimise the effects of construction on road traffic emissions, will also be considered by the Programme.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-05-22", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "48275"} , {"_value" : "48279"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-05-22T13:02:09.37Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-05-18", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Air Pollution"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the right hon. Member for East Hampshire, representing the Parliamentary Works Sponsor Body, what steps he will take to minimise air pollution in central London from the Restoration and Renewal project on the Palace of Westminster.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/411", "label" : {"_value" : "Biography information for Mr Barry Sheerman"} } , "tablingMemberConstituency" : {"_value" : "Huddersfield"} , "tablingMemberPrinted" : [{"_value" : "Mr Barry Sheerman"} ], "uin" : "48280"} , {"_about" : "http://data.parliament.uk/resources/1194414", "AnsweringBody" : [{"_value" : "Parliamentary Works Sponsor Body"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1194414/answer", "answerText" : {"_value" : "

The Restoration and Renewal Programme has conducted preliminary assessments of the potential benefits of promoting biodiversity as part of the restoration works, including the introduction of swift bricks and bird boxes, and the desirability of such measures will be subject to the requirements of both Houses. The potential inclusion of beehives will require more careful consideration, including the health and safety implications, while other measures could include ensuring that all planting is pollinator friendly. The Sponsor Body has also agreed a strategic objective for the Programme to optimise the environmental impacty of the Palace in its construction and operation, which has been endorsed by the Commissions of both Houses and will be kept under review as the Programme progresses.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3969", "label" : {"_value" : "Biography information for Damian Hinds"} } , "answeringMemberConstituency" : {"_value" : "East Hampshire"} , "answeringMemberPrinted" : {"_value" : "Damian Hinds"} , "dateOfAnswer" : {"_value" : "2020-05-19", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2020-05-19T13:58:39.103Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "207"} , "answeringDeptShortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "answeringDeptSortName" : {"_value" : "Parliamentary Works Sponsor Body"} , "date" : {"_value" : "2020-05-07", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Palace of Westminster: Repairs and Maintenance"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Right hon. Member for East Hampshire representing the Parliamentary Works Sponsor Body, what assessment he has made of the merits of including (a) swift bricks, (b) bird boxes, (c) beehives, and (d) others in the refurbishment of the Palace of Westminster.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3939", "label" : {"_value" : "Biography information for Andrew Percy"} } , "tablingMemberConstituency" : {"_value" : "Brigg and Goole"} , "tablingMemberPrinted" : [{"_value" : "Andrew Percy"} ], "uin" : "45120"} ], "itemsPerPage" : 10, "page" : 0, "startIndex" : 1, "totalResults" : 8, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }