{ "format" : "linked-data-api", "version" : "0.2", "result" : {"_about" : "http://eldaddp.azurewebsites.net/answeredquestions.text?max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "definition" : "http://eldaddp.azurewebsites.net/meta/answeredquestions.text?max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "extendedMetadataVersion" : "http://eldaddp.azurewebsites.net/answeredquestions.text?max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z&_metadata=all", "first" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=0&max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "hasPart" : "http://eldaddp.azurewebsites.net/answeredquestions.text?max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "isPartOf" : "http://eldaddp.azurewebsites.net/answeredquestions.text?max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "items" : [{"_about" : "http://data.parliament.uk/resources/1110116", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1110116/answer", "answerText" : {"_value" : "

The £48bn Control Period 6 funding settlement for the railway that Government announced in 2017 makes provision for the operation, maintenance and renewal of rail infrastructure between 2019 and 2024. It includes a £10.4bn provision for infrastructure enhancement projects. This is on top of new rolling stock, which is procured via separate arrangements.<\/p>

<\/p>

High Speed 2 (HS2) has a long-term funding envelope of £55.7bn (2015 prices). It is this government\u2019s largest capital programme and the benefits are largely for the North.<\/p>

<\/p>

The Government has committed £52m to continue to develop Northern Powerhouse Rail (NPR) this year. Decisions on future investment will be considered in the Spending Review. We are working with Transport for the North on their plans for NPR. The full benefits of NPR can only be achieved by integrating it with HS2 and given the status of the projects NPR needs HS2 to be built first.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4580", "label" : {"_value" : "Biography information for Baroness Vere of Norbiton"} } , "answeringMemberPrinted" : {"_value" : "Baroness Vere of Norbiton"} , "dateOfAnswer" : {"_value" : "2019-04-24", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-24T14:21:45.67Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-08", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Railways: Capital Investment"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government, further to the Written Answer by Baroness Sugg on 2 April (HL14685), of the £48 billion committed to investment in the rail network during Control Period 6, how much is for new (1) infrastructure, and (2) rolling stock; and what is the planned investment in HS2 and Northern Powerhouse Rail during the same period.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/738", "label" : {"_value" : "Biography information for Lord Alton of Liverpool"} } , "tablingMemberPrinted" : [{"_value" : "Lord Alton of Liverpool"} ], "uin" : "HL15085"} , {"_about" : "http://data.parliament.uk/resources/1110171", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1110171/answer", "answerText" : {"_value" : "

The Government has no plans to carry out such an assessment at present. Government funding for the Electric Vehicle Homecharge Scheme is focused on cars and vans, since they produce a much greater proportion of road transport emissions than motorcycles.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3991", "label" : {"_value" : "Biography information for Jesse Norman"} } , "answeringMemberConstituency" : {"_value" : "Hereford and South Herefordshire"} , "answeringMemberPrinted" : {"_value" : "Jesse Norman"} , "dateOfAnswer" : {"_value" : "2019-04-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-11T14:26:04.557Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-08", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Electric Vehicles: Charging Points"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, if his Department will make an assessment of the merits of extending the Electric Vehicle Homecharge Scheme to cover all electric motorcycles.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/4488", "label" : {"_value" : "Biography information for Martyn Day"} } , "tablingMemberConstituency" : {"_value" : "Linlithgow and East Falkirk"} , "tablingMemberPrinted" : [{"_value" : "Martyn Day"} ], "uin" : "242196"} , {"_about" : "http://data.parliament.uk/resources/1110186", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1110186/answer", "answerText" : {"_value" : "

<\/strong><\/p>

Business Area<\/p><\/td>

Number of induction meetings**<\/p><\/td>

Number of staff that attended the induction meetings<\/p><\/td>

Number of induction meetings at which the trade unions were invited to make a presentation at<\/p><\/td>

Number of induction meetings at which the trade unions were excluded from making a presentation at<\/p><\/td><\/tr>

Department for Transport (central department)<\/p><\/td>

12<\/p><\/td>

540*<\/p><\/td>

N/A<\/p><\/td>

N/A<\/p><\/td><\/tr>

Driver and Vehicle Licensing Agency<\/p><\/td>

15<\/p><\/td>

366<\/p><\/td>

15<\/p><\/td>

0<\/p><\/td><\/tr>

Driver and Vehicle Standards Agency<\/p><\/td>

27<\/p><\/td>

260<\/p><\/td>

27<\/p><\/td>

0<\/p><\/td><\/tr>

Maritime and Coastguard Agency<\/p><\/td>

0<\/p><\/td>

0<\/p><\/td>

N/A<\/p><\/td>

N/A<\/p><\/td><\/tr>

Vehicle Certification Agency<\/p><\/td>

1<\/p><\/td>

6<\/p><\/td>

0<\/p><\/td>

0<\/p><\/td><\/tr>

*Estimate only based on capacity of courses <\/em> **\u2019Induction meetings\u2019 refer to formal sessions for groups of new entrants, and not any other meeting that may form part of an individual induction plan<\/em><\/p><\/td><\/tr><\/tbody><\/table>

<\/p>

DfTc and VCA are in discussions with the trade union side about how to incorporate the trade union into the induction process. The induction materials given to new staff include information about joining a trade union.<\/p>

<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3991", "label" : {"_value" : "Biography information for Jesse Norman"} } , "answeringMemberConstituency" : {"_value" : "Hereford and South Herefordshire"} , "answeringMemberPrinted" : {"_value" : "Jesse Norman"} , "dateOfAnswer" : {"_value" : "2019-04-11", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-11T14:49:58.097Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-08", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Department for Transport: Trade Unions"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, pursuant to the Answer of 19 March to Question 232553 on Department for Transport: Trade Unions, how many induction meetings for new entrants were held in his Department in 2018; in how many of those meetings were trades unions (a) invited to make and (b) excluded from making a presentation; and how many staff attended those meetings.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/3973", "label" : {"_value" : "Biography information for Grahame Morris"} } , "tablingMemberConstituency" : {"_value" : "Easington"} , "tablingMemberPrinted" : [{"_value" : "Grahame Morris"} ], "uin" : "242109"} , {"_about" : "http://data.parliament.uk/resources/1109736", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109736/answer", "answerText" : {"_value" : "

A proposal for a new facility in Bescot is being developed by Network Rail to produce the sleepers necessary for them to maintain, renew, and enhance our rail network. The facility is intended to make up the shortfall when an existing facility at Washwood Heath is closed to become an HS2 depot.<\/p>

<\/p>

The Network Rail facility at Doncaster is not capable of being extended to increase capacity. The facility itself is entirely surrounded by adjacent development, railway lines, railway depots, housing and roads. It is operating at full capacity and only able to deliver production of 400,000 sleepers each year.<\/p>

<\/p>

Additionally, Network Rail require a geographically separate, second facility to avoid the supply chain risk of a single point of failure, should anything prevent production at a facility.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3996", "label" : {"_value" : "Biography information for Andrew Jones"} } , "answeringMemberConstituency" : {"_value" : "Harrogate and Knaresborough"} , "answeringMemberPrinted" : {"_value" : "Andrew Jones"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T08:16:32.87Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-04", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Railways: Birmingham"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, what assessment he has made of the feasibility of Network Rail's sleeper factory at Doncaster meeting the shortfall in production capacity in the event of the potential closure of Network Rail\u2019s exiting sleeper factory at Washwood Heath, Birmingham.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1463", "label" : {"_value" : "Biography information for Lord Watson of Wyre Forest"} } , "tablingMemberConstituency" : {"_value" : "West Bromwich East"} , "tablingMemberPrinted" : [{"_value" : "Tom Watson"} ], "uin" : "240984"} , {"_about" : "http://data.parliament.uk/resources/1109750", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109750/answer", "answerText" : {"_value" : "

A proposal for a new facility in Bescot is being developed by Network Rail to produce the sleepers necessary for them to maintain, renew, and enhance our rail network. The facility is intended to make up the shortfall when an existing facility at Washwood Heath is closed to become an HS2 depot.<\/p>

<\/p>

Network Rail is a customer of Cemex who own and operate the facility at Washwood Heath. Production is planned to cease at this facility on 14 June 2019. The HS2 programme requires vacant possession of the site in August 2019 to enable construction works to proceed.<\/p>

<\/p>

I have no plans to make a statement about the proposed facility.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/3996", "label" : {"_value" : "Biography information for Andrew Jones"} } , "answeringMemberConstituency" : {"_value" : "Harrogate and Knaresborough"} , "answeringMemberPrinted" : {"_value" : "Andrew Jones"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T08:14:08.977Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-04", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Railways: Birmingham"} , "houseId" : {"_value" : "1"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25259", "prefLabel" : {"_value" : "House of Commons"} } ], "questionText" : "To ask the Secretary of State for Transport, on what date Network Rail will cease production of railway sleepers at its factory in Washwood Heath, Birmingham; whether there is capacity to extend production beyond this date; and if he will make a statement.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/1463", "label" : {"_value" : "Biography information for Lord Watson of Wyre Forest"} } , "tablingMemberConstituency" : {"_value" : "West Bromwich East"} , "tablingMemberPrinted" : [{"_value" : "Tom Watson"} ], "uin" : "240985"} , {"_about" : "http://data.parliament.uk/resources/1109280", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109280/answer", "answerText" : {"_value" : "

The HS2 Phase One Main Civil Contracts were signed in July 2017 and Phase One design development and enabling works are continuing to progress. Notice to Proceed is the formal contractual process which enables each Phase One supplier to move from design and development to construction.<\/p>

<\/p>

HS2 Ltd has advised the Government that it intends for Notice to Proceed to take place later in 2019 to allow it to finalise costs and plans with its contracted suppliers. Full construction of bridges and tunnels will commence following award of Notice to Proceed. Essential works to prepare the route for this stage are well underway, with over 60 active sites, including major works at Euston, Old Oak Common, Curzon Street and Washwood Heath.<\/p>

<\/p>

Expenditure on HS2 to date is set out in the Annual Report and Accounts of HS2 Ltd and the Department for Transport. The Government has committed to update Parliament on HS2\u2019s progress at least once a year.<\/p>

<\/p>

The Phase One Full Business Case, planned for publication later in 2019, will include an updated estimate of cost and schedule and an accompanying assessment of benefits.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "HL14998"} , {"_value" : "HL14999"} , {"_value" : "HL15000"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T10:07:36.55Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-02", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government why the notice to proceed with the HS2 project has been delayed.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/134", "label" : {"_value" : "Biography information for Lord Framlingham"} } , "tablingMemberPrinted" : [{"_value" : "Lord Framlingham"} ], "uin" : "HL14997"} , {"_about" : "http://data.parliament.uk/resources/1109281", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109281/answer", "answerText" : {"_value" : "

The HS2 Phase One Main Civil Contracts were signed in July 2017 and Phase One design development and enabling works are continuing to progress. Notice to Proceed is the formal contractual process which enables each Phase One supplier to move from design and development to construction.<\/p>

<\/p>

HS2 Ltd has advised the Government that it intends for Notice to Proceed to take place later in 2019 to allow it to finalise costs and plans with its contracted suppliers. Full construction of bridges and tunnels will commence following award of Notice to Proceed. Essential works to prepare the route for this stage are well underway, with over 60 active sites, including major works at Euston, Old Oak Common, Curzon Street and Washwood Heath.<\/p>

<\/p>

Expenditure on HS2 to date is set out in the Annual Report and Accounts of HS2 Ltd and the Department for Transport. The Government has committed to update Parliament on HS2\u2019s progress at least once a year.<\/p>

<\/p>

The Phase One Full Business Case, planned for publication later in 2019, will include an updated estimate of cost and schedule and an accompanying assessment of benefits.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "HL14997"} , {"_value" : "HL14999"} , {"_value" : "HL15000"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T10:07:36.627Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-02", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government when the contracts for carrying out the major construction works for HS2 will be signed.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/134", "label" : {"_value" : "Biography information for Lord Framlingham"} } , "tablingMemberPrinted" : [{"_value" : "Lord Framlingham"} ], "uin" : "HL14998"} , {"_about" : "http://data.parliament.uk/resources/1109282", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109282/answer", "answerText" : {"_value" : "

The HS2 Phase One Main Civil Contracts were signed in July 2017 and Phase One design development and enabling works are continuing to progress. Notice to Proceed is the formal contractual process which enables each Phase One supplier to move from design and development to construction.<\/p>

<\/p>

HS2 Ltd has advised the Government that it intends for Notice to Proceed to take place later in 2019 to allow it to finalise costs and plans with its contracted suppliers. Full construction of bridges and tunnels will commence following award of Notice to Proceed. Essential works to prepare the route for this stage are well underway, with over 60 active sites, including major works at Euston, Old Oak Common, Curzon Street and Washwood Heath.<\/p>

<\/p>

Expenditure on HS2 to date is set out in the Annual Report and Accounts of HS2 Ltd and the Department for Transport. The Government has committed to update Parliament on HS2\u2019s progress at least once a year.<\/p>

<\/p>

The Phase One Full Business Case, planned for publication later in 2019, will include an updated estimate of cost and schedule and an accompanying assessment of benefits.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "HL14997"} , {"_value" : "HL14998"} , {"_value" : "HL15000"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T10:07:36.673Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-02", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government when they expect to start work on bridges and tunnels on the HS2 project.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/134", "label" : {"_value" : "Biography information for Lord Framlingham"} } , "tablingMemberPrinted" : [{"_value" : "Lord Framlingham"} ], "uin" : "HL14999"} , {"_about" : "http://data.parliament.uk/resources/1109283", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109283/answer", "answerText" : {"_value" : "

The HS2 Phase One Main Civil Contracts were signed in July 2017 and Phase One design development and enabling works are continuing to progress. Notice to Proceed is the formal contractual process which enables each Phase One supplier to move from design and development to construction.<\/p>

<\/p>

HS2 Ltd has advised the Government that it intends for Notice to Proceed to take place later in 2019 to allow it to finalise costs and plans with its contracted suppliers. Full construction of bridges and tunnels will commence following award of Notice to Proceed. Essential works to prepare the route for this stage are well underway, with over 60 active sites, including major works at Euston, Old Oak Common, Curzon Street and Washwood Heath.<\/p>

<\/p>

Expenditure on HS2 to date is set out in the Annual Report and Accounts of HS2 Ltd and the Department for Transport. The Government has committed to update Parliament on HS2\u2019s progress at least once a year.<\/p>

<\/p>

The Phase One Full Business Case, planned for publication later in 2019, will include an updated estimate of cost and schedule and an accompanying assessment of benefits.<\/p>

<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "groupedQuestionUIN" : [{"_value" : "HL14997"} , {"_value" : "HL14998"} , {"_value" : "HL14999"} ], "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T10:07:36.72Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-02", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "High Speed 2 Line"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government, further to reports that HS2 will cost twice its original estimate, what steps they are taking to conduct an urgent review of its costs to date; and whether they will publish the results of that review.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/134", "label" : {"_value" : "Biography information for Lord Framlingham"} } , "tablingMemberPrinted" : [{"_value" : "Lord Framlingham"} ], "uin" : "HL15000"} , {"_about" : "http://data.parliament.uk/resources/1109288", "AnsweringBody" : [{"_value" : "Department for Transport"} ], "answer" : {"_about" : "http://data.parliament.uk/resources/1109288/answer", "answerText" : {"_value" : "

On 22 November 2018, the Government published a two-year action plan and response to the Cycling and Walking Investment Strategy (CWIS) Safety Review Call for Evidence. This made clear its commitment to the hierarchy of road users.<\/p>

Included within CWIS SR action plan is a commitment to review the guidance in The Highway Code to improve safety for cyclists and pedestrians. We are currently agreeing the scope and delivery of this review, and would expect the hierarchy of road users to fall within scope. The review will be conducted in consultation with the Department's stakeholders, according to its usual practice.<\/p>"} , "answeringMember" : {"_about" : "http://data.parliament.uk/members/4584", "label" : {"_value" : "Biography information for Baroness Sugg"} } , "answeringMemberPrinted" : {"_value" : "Baroness Sugg"} , "dateOfAnswer" : {"_value" : "2019-04-12", "_datatype" : "dateTime"} , "isMinisterialCorrection" : {"_value" : "false", "_datatype" : "boolean"} , "questionFirstAnswered" : [{"_value" : "2019-04-12T10:06:20.85Z", "_datatype" : "dateTime"} ]} , "answeringDeptId" : {"_value" : "27"} , "answeringDeptShortName" : {"_value" : "Transport"} , "answeringDeptSortName" : {"_value" : "Transport"} , "date" : {"_value" : "2019-04-02", "_datatype" : "dateTime"} , "hansardHeading" : {"_value" : "Highway Code"} , "houseId" : {"_value" : "2"} , "legislature" : [{"_about" : "http://data.parliament.uk/terms/25277", "prefLabel" : {"_value" : "House of Lords"} } ], "questionText" : "To ask Her Majesty's Government what consideration they have given, as part of their review of the Highway Code, to changing from the current position where all road users are deemed to have equal responsibility to a hierarchy of responsibility so those categories of users who cause the greatest harm have the greatest responsibility for reducing the dangers that they pose to others.", "registeredInterest" : {"_value" : "false", "_datatype" : "boolean"} , "tablingMember" : {"_about" : "http://data.parliament.uk/members/2024", "label" : {"_value" : "Biography information for Lord Hunt of Kings Heath"} } , "tablingMemberPrinted" : [{"_value" : "Lord Hunt of Kings Heath"} ], "uin" : "HL15005"} ], "itemsPerPage" : 10, "next" : "http://eldaddp.azurewebsites.net/answeredquestions.text?_page=1&max-ddpCreated=2019-04-08T23%3A01%3A04.717Z&AnsweringBody.=Department+for+Transport&min-answer.questionFirstAnswered.=2019-04-11T12%3A17%3A54.91Z", "page" : 0, "startIndex" : 1, "totalResults" : 12, "type" : ["http://purl.org/linked-data/api/vocab#ListEndpoint", "http://purl.org/linked-data/api/vocab#Page"]} }