<p>Her Majesty's Government welcomed the National Audit Office report on the Defence
Nuclear Enterprise, which set out the complex nature of the enterprise, and recognised
the positive steps that have been taken to deliver this technically challenging network
of programmes.</p><p>The Dreadnought programme is one of the most complex engineering
programmes ever undertaken by the United Kingdom. It remains on schedule to deliver
the first of class into service in the early 2030s and within the £31 billion estimated
cost as stated in Strategic Defence and Security Review 2015.</p>
|
|