446889
registered interest false more like this
date less than 2016-01-21more like thismore than 2016-01-21
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Bexleyheath Line: Landslips more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, pursuant to the Answer of 19 January 2016 to Question 22574, for what reasons, during the closure of the Bexleyheath rail line during the week beginning 11 January 2016, (a) Southeastern services on adjacent lines were cancelled, (b) there was a lack of information about alternative services and (c) staff had no information to pass onto customers about alternative services or when replacement bus services would arrive; what systems were put in place to communicate regular updates of information to staff so customers could be given accurate advice; what advice was given to staff regarding assistance for people with disabilities; what steps he is taking to determine whether the responses to the situation from Network Rail and Southeastern were adequate; and if he will make a statement. more like this
tabling member constituency Eltham more like this
tabling member printed
Clive Efford more like this
uin 23672 remove filter
answer
answer
is ministerial correction false more like this
date of answer less than 2016-01-26more like thismore than 2016-01-26
answer text <br /><p>Following the unfortunate landslip at Barnehust, it was necessary to close the line serving Bexleyheath in order that repairs could be carried out.</p><br /><p>As a result of the Bexleyheath line closure, Southeastern have had to run more trains on the adjacent lines to provide extra capacity for passengers. This led to minimal cancellations to the scheduled timetable on adjacent lines.</p><br /><p>Information regarding alternative travel arrangements was provided by posters at affected stations, station announcements, on National Rail Industry systems, the Southeastern website and on social media.</p><br /><p>Staff were given regular updates on the alternative travel arrangements and station announcements were made where appropriate. Replacement buses were in operation between Lewisham and Dartford via Bexleyheath in both directions. Other bus services were accepting Southeastern tickets, additionally, Docklands Light Railway and London Underground were accepting tickets where appropriate. Regular updates were provided to station management, who provided briefings to their station staff. The Passenger Assist service was in effect and Southeastern staff were advised to book taxis from stations that were not accessible for those passengers who required them.</p><br /><p>My officials were in regular contact with Southeastern and Network Rail, who ensured that the line was opened as quickly as possible and that passengers were kept informed at all times.</p><br />
answering member constituency Devizes more like this
answering member printed Claire Perry more like this
question first answered
less than 2016-01-26T12:26:52.05Zmore like thismore than 2016-01-26T12:26:52.05Z
answering member
3974
label Biography information for Claire Perry more like this
tabling member
165
label Biography information for Clive Efford more like this