answer text |
<p>DBS publishes its performance data on a quarterly basis. For the third quarter
of 2023-24, DBS achieved the following performance:</p><p> </p><p>The target to process
85% of Basic checks within 2 days was met, with an average attainment of 88.1%. The
85% target was met on day 2 and the average turnaround time was 0.9 days.</p><p> </p><p>The
target to process 85% of Standard checks within 5 days was met, with an average attainment
of 88.5%, the 85% target was met on day 3 and the average turnaround time was 1.5
days.</p><p> </p><p>The target to process 80% of Enhanced checks within 14 days was
not met during the quarter, with an average attainment of 76.7%. The 80% target was
met on day 18 and the average turnaround time was 11.5 days.</p><p> </p><p>For the
Canterbury constituency, the average turnaround time between 1/04/2023 and 31/12/2023
was 19.8 days for Enhanced checks and 1.3 days for Standard checks.</p><p> </p><p>For
the Kent, the average turnaround time between 1/04/2023 and 31/12/2023 was 19.9 days
for Enhanced checks and 1.3 days for Standard checks.</p>
|
|