question text To ask Her Majesty's Government what is their assessment of the reasons for the delay in implementing the Connecting Devon and Somerset Programme announced in 2013 that aims to ensure that 90 per cent of premises have access to fibre optic broadband by the end of 2016, and of the effect of that delay on business competitiveness within the South Somerset area. more like this
tabling member printed
Lord Patten remove filter
uin HL6916 remove filter
answer
answer
is ministerial correction false more like this
date of answer less than 2014-05-13more like thismore than 2014-05-13
answer text <p>The Connecting Devon and Somerset project is scheduled to deliver superfast availability to 268,494 premises by March 2016. It is currently on track to reach this target and will have delivered to 70,000 premises by the end of July 2014, despite some delays caused by flooding.</p><p> </p> more like this
answering member printed Lord Gardiner of Kimble more like this
question first answered
less than 2014-05-13T12:00:00.00Zmore like thismore than 2014-05-13T12:00:00.00Z
answering member
4161
label Biography information for Lord Gardiner of Kimble more like this
tabling member
1137
label Biography information for Lord Patten more like this