<p>All of the funding required is in place for the remaining work at West Ealing,
Ealing Broadway and Acton Main Line. The Department for Transport has regular discussions
with Network Rail and Crossrail Limited regarding the Network Rail works. Network
Rail closely monitors its finances through monthly reporting to Crossrail Limited.</p><p>
</p><p>In Control Period 5, £16.6m of funding was allocated to the build elements
of the Crossrail station upgrade works at West Ealing, Ealing Broadway and Acton Main
Line. Of this funding £16.6m has been spent.</p><p> </p><p>In Control Period 6, £64.4m
of funding has been allocated to the Crossrail station upgrade works at West Ealing,
Ealing Broadway and Acton Main Line.</p>
|
|