<p>Please find below the total spend on consultancy for HMCTS for the period requested.
Please note the spend is taken from our Bravo spend tool and is an accurate figure
of what has been invoiced within this period:</p><p> </p><p>(i) 2016-17 = £3,103,764.16</p><p>(ii)
2017-18 = £11,805,649.04</p><p> </p><p>Please see below table which outlines the consultancy
projects for the periods requested for HMCTS, the information includes start dates,
contract values and descriptions of the services:</p><p> </p><table><tbody><tr><td><p>Start
Date</p></td><td><p>Supplier</p></td><td><p>Total Value of Contract</p></td></tr><tr><td><p>2016/17</p></td><td><p>BMT
Hi-Q Sigma</p></td><td><p>£150,000</p></td></tr><tr><td><p>2016/17</p></td><td><p>Capita</p></td><td><p>£795,000</p></td></tr><tr><td><p>2016/17</p></td><td><p>Concerto
Partners LLP</p></td><td><p>£258,980</p></td></tr><tr><td><p>2016/17</p></td><td><p>Ernst
& Young LLP</p></td><td><p>£6,236,775</p></td></tr><tr><td><p>2016/17</p></td><td><p>KPMG
LLP</p></td><td><p>£1,129,875</p></td></tr><tr><td><p>2016/17</p></td><td><p>PA Consulting
Services Limited</p></td><td><p>£2,415,319</p></td></tr><tr><td><p>2016/17</p></td><td><p>PricewaterhouseCoopers
LLP</p></td><td><p>£107,800</p></td></tr><tr><td><p>2017/18</p></td><td><p>Allen Lane
Consultancy Limited</p></td><td><p>£3,657,750</p></td></tr><tr><td><p>2017/18</p></td><td><p>Deloitte
LLP</p></td><td><p>£462,040</p></td></tr><tr><td><p>2017/18</p></td><td><p>Methods
Business and Digital</p></td><td><p>£1,997,000</p></td></tr><tr><td><p>2017/18</p></td><td><p>PricewaterhouseCoopers
LLP</p></td><td><p>£30,000,000</p></td></tr><tr><td><p>2017/18</p></td><td><p>Veracity
Consulting</p></td><td><p>£681,015</p></td></tr></tbody></table><p> </p><p> </p><p>Consultants
are engaged to deliver short-term on projects where specialist skills required are
not available within the organisation. As part of the governance process, approvals
are sought from Finance Business Partner, HR Business Partner & the Director General
to ensure that project outcomes and budget are validated and to seek confirmation
that internal resource is not available to deliver either due to the specialist nature
of the project or due to capacity issues enabling delivery within the project timescales.</p><p><br>
By making use of consultants, the department can save on salary, national insurance
and pension costs associated with permanently employing individuals whose skills may
not be needed after a set period.</p><p> </p><p>The government is investing £1bn to
reform our courts and tribunals service, bringing new technology and modern ways of
working to the justice system and benefiting all those that use it.</p>
|
|