914760
registered interest false more like this
date less than 2018-06-01more like thismore than 2018-06-01
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Railways: Devon more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, when he plans to announce funding for additional railway resilience work at Dawlish and Teignmouth. more like this
tabling member constituency Plymouth, Sutton and Devonport more like this
tabling member printed
Luke Pollard remove filter
uin 149091 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2018-06-11more like thismore than 2018-06-11
answer text <p>The Department for Transport has already provided £15m funding for Network Rail to undertake development work on schemes to improve the resilience of the line through Dawlish and Teignmouth, in addition to the £40m spent by Network Rail to repair the damage caused by the 2014 storm. This is a highly unique and complex terrain and in order to deliver the best solution it is critical that the resilience study is comprehensive. The development work encompassing ground investigations, option selection and outline design is expected to be complete in 2019. A decision about the next phase of work and the funding for that can then be made.</p> more like this
answering member constituency Orpington more like this
answering member printed Joseph Johnson more like this
question first answered
less than 2018-06-11T16:40:50.27Zmore like thismore than 2018-06-11T16:40:50.27Z
answering member
4039
label Biography information for Lord Johnson of Marylebone more like this
tabling member
4682
label Biography information for Luke Pollard more like this