answer text |
<p>The Senior Deputy Speaker has asked me, as Chairman of the Services Committee,
to respond on his behalf. To fabricate temporary doors more in keeping with the original
doors would be extremely costly and would delay the programme well beyond the compliance
deadline date. Such a door would require the alteration of the original frame which
would not be permitted under current listed building permissions.</p><p>No consideration
has been given to replace the temporary doors given the deadline to achieve life safety
compliance, compliance with British Standards and Building Regulations, and the additional
cost of replacement. The original doors will be returned between mid-November and
the end of November.</p><p> </p>
|
|