hansard heading Heathrow Airport: Railways more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what consultation he undertook before postponing the delivery of the Western Rail Access to Heathrow. more like this
tabling member constituency Plymouth, Sutton and Devonport more like this
tabling member printed
Luke Pollard more like this
uin 99729 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2020-10-14more like thismore than 2020-10-14
answer text <p>The Department has not postponed the delivery of the Western Rail Access to Heathrow. The Government has always been clear that delivery of such is subject to a satisfactory business case and agreement of acceptable terms with the Heathrow Aviation industry. Discussions between the Department and Heathrow Airport Limited to agree an appropriate funding contribution were interrupted following the Court of Appeal’s judgement on the Airports National Policy Statement and the devastating impact of COVID-19, resulting in a delay. Network Rail plans to re-consult on the scheme in 2021.</p><p> </p><p> </p> more like this
answering member constituency Daventry more like this
answering member printed Chris Heaton-Harris more like this
question first answered
less than 2020-10-14T13:51:06.243Zmore like thismore than 2020-10-14T13:51:06.243Z
answering member
3977
label Biography information for Chris Heaton-Harris more like this
tabling member
4682
label Biography information for Luke Pollard more like this
1240802
registered interest false more like this
date remove filter
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Heathrow Airport: Railways more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, when construction work will start on the Western Rail Access to Heathrow. more like this
tabling member constituency Plymouth, Sutton and Devonport more like this
tabling member printed
Luke Pollard more like this
uin 99730 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2020-10-14more like thismore than 2020-10-14
answer text <p>Construction of the Western Rail Link to Heathrow is expected to start following the granting of planning consent, with construction of the main build estimated to take approximately five years. Submission of the scheme’s application for development consent, is subject to a satisfactory business case and the agreement of acceptable terms with the Heathrow Aviation industry.</p><p> </p> more like this
answering member constituency Daventry more like this
answering member printed Chris Heaton-Harris more like this
question first answered
less than 2020-10-14T13:25:24.05Zmore like thismore than 2020-10-14T13:25:24.05Z
answering member
3977
label Biography information for Chris Heaton-Harris more like this
tabling member
4682
label Biography information for Luke Pollard more like this
1240803
registered interest false more like this
date remove filter
answering body
Department for Transport more like this
answering dept id 27 more like this
answering dept short name Transport more like this
answering dept sort name Transport more like this
hansard heading Heathrow Airport: Railways more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Transport, what estimate he has made of the potential cost increase as a result of the two year delay to the Western Rail Access to Heathrow project. more like this
tabling member constituency Plymouth, Sutton and Devonport more like this
tabling member printed
Luke Pollard more like this
uin 99731 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2020-10-14more like thismore than 2020-10-14
answer text <p>Progress on the Western Rail Link to Heathrow is subject to a satisfactory business case and the agreement of acceptable terms with the Heathrow aviation industry. Negotiations on these terms have not yet concluded and any estimate of cost to the taxpayer is dependent on this agreement. There is also no reason why costs would increase as a result.</p> more like this
answering member constituency Daventry more like this
answering member printed Chris Heaton-Harris more like this
question first answered
less than 2020-10-14T13:34:57.983Zmore like thismore than 2020-10-14T13:34:57.983Z
answering member
3977
label Biography information for Chris Heaton-Harris more like this
tabling member
4682
label Biography information for Luke Pollard more like this