Linked Data API

Show Search Form

Search Results

1126528
registered interest false more like this
date remove filter
answering body
Ministry of Housing, Communities and Local Government more like this
answering dept id 7 more like this
answering dept short name Housing, Communities and Local Government more like this
answering dept sort name Housing, Communities and Local Government more like this
hansard heading High Rise Flats: Insulation more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Housing, Communities and Local Government, whether his Department has calculated the average cost per block of remediating aluminium composite cladding. more like this
tabling member constituency Croydon North more like this
tabling member printed
Mr Steve Reed more like this
uin 254196 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2019-05-20more like thismore than 2019-05-20
answer text <p>On 9 May, The Government announced its commitment to fully fund the remediation of private sector high-rise residential blocks with unsafe Aluminium Composite Material cladding. £200 million has been set aside for this. We will publish the full fund application guidance including eligibility and evidence criteria by mid-July and we expect that the formal application process will begin in the Summer.</p> more like this
answering member constituency North West Hampshire more like this
answering member printed Kit Malthouse more like this
grouped question UIN 254195 more like this
question first answered
less than 2019-05-20T16:18:50.75Zmore like thismore than 2019-05-20T16:18:50.75Z
answering member
4495
label Biography information for Kit Malthouse more like this
tabling member
4268
label Biography information for Steve Reed more like this