answer text |
<p>The Ministry of Defence, the Scottish Environmental Protection Agency and Fife
Council continue to work together to implement the agreed Management Strategy for
the long-term management of radium contamination at Dalgety Bay.</p><p>Remediation
is due to physically begin in April 2020 and be completed in September of the same
year. The second phase of work is planned to begin in April 2021 and be completed
in September 2021. Work cannot take place outside of these periods due to the disturbance
that may be caused to wintering birds.</p>
|
|