100614
registered interest false more like this
date remove filter
answering body
Department for Energy and Climate Change more like this
answering dept id 63 more like this
answering dept short name Energy and Climate Change more like this
answering dept sort name Energy and Climate Change more like this
hansard heading Renewable Energy more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty’s Government what allowance is made in future costings of renewable energy for weather conditions, such as when wind or solar power are not available. more like this
tabling member printed
Lord Hunt of Chesterton more like this
uin HL2345 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2014-11-04more like thismore than 2014-11-04
answer text <p>Estimates of the levelised costs of electricity generation for different technologies are published by DECC. The levelised cost of a particular generation technology is the ratio of the total costs of a generic plant to the total amount of electricity expected to be generated over the plant’s lifetime (per megawatt hour). Where relevant, estimates of electricity generation make an allowance for weather conditions based on estimates of when the relevant energy source is expected to be available, on average, over a plant’s lifetime (load factors). This is the case for intermittent renewable technologies such as onshore wind and solar photovoltaic.</p><p>Levelised cost estimates also depend on other assumptions, including capital costs, fuel and EU ETS allowance prices, operating costs, discount rates and other drivers. This means that there is a range around levelised cost estimates.</p><p>The DECC Electricity Generation Costs (December 2013) report contains DECC’s latest levelised cost estimates.</p>
answering member printed Baroness Verma more like this
question first answered
less than 2014-11-04T15:13:19.9230669Zmore like thismore than 2014-11-04T15:13:19.9230669Z
answering member
3790
label Biography information for Baroness Verma more like this
attachment
1
file name Electricity Generation Costs Report December 2013.pdf more like this
title Electricity Generation Costs Report December 2013 more like this
tabling member
2543
label Biography information for Lord Hunt of Chesterton more like this