Linked Data API

Show Search Form

Search Results

1681539
registered interest false more like this
date less than 2024-01-11more like thismore than 2024-01-11
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading Trident Submarines: Procurement more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Defence, what recent estimate he has made of the total lifetime cost of the Trident renewal programme. more like this
tabling member constituency Glasgow North more like this
tabling member printed
Patrick Grady more like this
uin 9231 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2024-01-22more like thismore than 2024-01-22
answer text <p>The Dreadnought submarine programme remains within overall budget and on track for the first of class, HMS Dreadnought, to enter service in the early 2030s.</p><p> </p><p>Inflation has remained higher than expected for an extended period and had an adverse impact on the cost forecasts for this programme when compared to the forecasts from a year earlier.</p><p> </p><p>As the programme is in its preliminary phases, it is too early to provide cost estimates for the replacement warhead programme.</p> more like this
answering member constituency South Suffolk more like this
answering member printed James Cartlidge more like this
grouped question UIN 9232 more like this
question first answered
less than 2024-01-22T17:55:56.327Zmore like thismore than 2024-01-22T17:55:56.327Z
answering member
4519
label Biography information for James Cartlidge more like this
tabling member
4432
label Biography information for Patrick Grady more like this