794220
registered interest false more like this
date remove filter
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading Frigates: Procurement more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government what assessment they have made of the sufficiency of the management and technical resources within the Ministry of Defence to manage both the Type 26 and Type 31a programmes at the same time; and how many (1) Defence Equipment and Support, and (2) Royal Navy, staff they estimate will be needed to manage each of those programmes at their peaks. more like this
tabling member printed
Lord Moonie more like this
uin HL3538 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-12-04more like thismore than 2017-12-04
answer text <p>The Ministry of Defence is satisfied with the number of people and balance of capability dedicated to each programme, in both Navy Command and Defence Equipment and Support (DE&amp;S), and has a plan to increase those resources to respond to the needs of both the Type 26 and Type 31e programmes in the future.</p><p>The transformation of DE&amp;S has introduced a balanced matrix management structure, which allows specialist resources to be deployed more easily to meet the demands of equipment procurement projects.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2017-12-04T17:25:32.963Zmore like thismore than 2017-12-04T17:25:32.963Z
answering member
2000
label Biography information for Earl Howe more like this
tabling member
621
label Biography information for Lord Moonie more like this
794221
registered interest false more like this
date remove filter
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading Type 45 Destroyers more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government how many staff worked on the Type 45 Integrated Project Team; what was the average number of staff working on that team at any one time; and what was the maximum number. more like this
tabling member printed
Lord Moonie more like this
uin HL3539 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-12-04more like thismore than 2017-12-04
answer text <p>At the start of the Type 45 destroyer procurement programme in 2000, the Project Team comprised approximately 44 members of staff. The team grew to its peak in 2006, when the numbers had increased to approximately 110 people. By 2014, when the build of the ships was complete, this number had reduced to a minimal skeleton staff.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2017-12-04T17:26:04.263Zmore like thismore than 2017-12-04T17:26:04.263Z
answering member
2000
label Biography information for Earl Howe more like this
tabling member
621
label Biography information for Lord Moonie more like this
794223
registered interest false more like this
date remove filter
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading Fleet Solid Support Ships: Shipbuilding more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government whether future Fleet Support Ships will be built in yards in the UK; and if so where. more like this
tabling member printed
Lord Moonie more like this
uin HL3541 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-12-04more like thismore than 2017-12-04
answer text <p>As set out in the National Shipbuilding Strategy, procurement of naval support ships, such as the Fleet Solid Support ships, will be by international competition to ensure maximum value for money for the UK taxpayer. UK shipyards are encouraged to engage in the competitive process.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2017-12-04T17:11:34.417Zmore like thismore than 2017-12-04T17:11:34.417Z
answering member
2000
label Biography information for Earl Howe more like this
tabling member
621
label Biography information for Lord Moonie more like this
794224
registered interest false more like this
date remove filter
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading F-35 Aircraft more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government what is the total exchange rate contingency for the new Joint Strike Fighters for which orders have already been placed. more like this
tabling member printed
Lord Moonie more like this
uin HL3542 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-12-04more like thismore than 2017-12-04
answer text <p>For the UK F-35 Lightning Programme our cost approvals include some provision to address foreign exchange rate risks. Depending on the stage of the programme, the senior responsible owner and the project team will manage an appropriate risk contingency of 5-10 per cent, which is dynamically managed and proportionate to the risks at that time. This will continue to be monitored and prioritised as necessary in accordance with the overall departmental position.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2017-12-04T17:12:42.117Zmore like thismore than 2017-12-04T17:12:42.117Z
answering member
2000
label Biography information for Earl Howe more like this
tabling member
621
label Biography information for Lord Moonie more like this
794225
registered interest false more like this
date remove filter
answering body
Ministry of Defence more like this
answering dept id 11 more like this
answering dept short name Defence more like this
answering dept sort name Defence more like this
hansard heading F-35 Aircraft more like this
house id 2 more like this
legislature
25277
pref label House of Lords more like this
question text To ask Her Majesty's Government with whom they have negotiated (1) the price, and (2) delivery, for the new Joint Strike Fighters. more like this
tabling member printed
Lord Moonie more like this
uin HL3543 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2017-12-04more like thismore than 2017-12-04
answer text <p>On behalf of all the F-35 partner nations, the United States Joint Program Office negotiates the price and delivery targets for all F-35 aircraft with its suppliers. The UK, in turn, discusses its own F-35 delivery dates with the Joint Program Office.</p> more like this
answering member printed Earl Howe more like this
question first answered
less than 2017-12-04T17:12:03.573Zmore like thismore than 2017-12-04T17:12:03.573Z
answering member