<p>The Department has not estimated the value of work accruing to UK manufacturing
companies in each region from the development of the Rampion wind farm.</p><p>In November
2014 the Offshore Wind Industry Council adopted an industry-wide methodology for reporting
on UK Content. This reporting helps industry hold itself to account on the commitment
to reach 50% UK content, while charting progress and reporting to a wider public.
This figure will show total UK content and break this down into the three main phases
of development (devex), manufacture & construction (capex) and operation (opex).</p><p>The
first data will be submitted to RenewableUK by industry in summer 2015 for publication
later in the year.</p>
|
|