<p>The anticipated outturn costs cannot be provided. The current approved costs and
in-service dates for Project Mensa and Project Pegasus are shown below.</p><p> </p><p>In-service
dates are shown in bandings to avoid prejudice to national security and defence.</p><p>
</p><p>The Main Gate business cases for Projects Mensa and Pegasus include estimates
for risk and uncertainty, which are contained within the approved costs.</p><p> </p><p>
</p><table><tbody><tr><td><p><strong>Project</strong></p></td><td><p><strong>In-service
period</strong></p></td><td><p><strong>Approved cost (£million)</strong></p></td></tr><tr><td><p>Project
Mensa (warhead assembly/disassembly)</p></td><td><p>2016-20</p></td><td><p>734</p></td></tr><tr><td><p>Project
Pegasus (uranium components)</p></td><td><p>2016-20</p></td><td><p>634</p></td></tr></tbody></table><p>
</p><p> </p>
|
|