hansard heading Hinkley Point C Power Station and Sizewell C Power Station more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Energy Security and Net Zero, what recent estimate her Department has made of when the (a) Hinkley and (b) Sizewell nuclear power plant will be operational. more like this
tabling member constituency West Lancashire remove filter
tabling member printed
Ashley Dalton more like this
uin 4020 more like this
answer
answer
is ministerial correction false more like this
date of answer remove maximum value filtermore like thismore than 2023-11-30
answer text <p>EDF is the lead investor at Hinkley Point C and they have provided a target date for commercial operations for Unit Reactor 1 of June 2027, with Unit Reactor 2 following a year later in June 2028. Both units have a risk of a delay of 15 months. We expect Sizewell C to be generating power from the mid-2030s, subject to ongoing project development and the timing of a Final Investment Decision.</p> more like this
answering member constituency West Aberdeenshire and Kincardine more like this
answering member printed Andrew Bowie more like this
question first answered
remove filter
answering member
4601
label Biography information for Andrew Bowie more like this
tabling member
4981
label Biography information for Ashley Dalton more like this