answer text |
<p>As of 12 July, 2018, fourteen publicly-owned buildings (including schools and hospitals)
have failed large-scale system tests on their cladding systems. One building has now
completed the remediation process, including removal and replacement of its aluminium
composite material cladding. The other building owners are working with the relevant
fire and rescue service and other specialists to consider remedial work, and are taking
account of building users’ needs when they do so. We are not aware of any high-rise
care homes with aluminium composite material cladding systems.</p><p>We are working
with the Department of Health and Social Care, NHS Improvement and Department for
Education to ensure that appropriate remediation steps are being taken on public buildings.</p><p>
</p>
|
|