hansard heading Sizewell B Power Station more like this
house id 1 more like this
legislature
25259
pref label House of Commons more like this
question text To ask the Secretary of State for Energy and Climate Change, what information she has been provided by the Office for Nuclear Regulation to demonstrate the safety of Sizewell B nuclear plant restarting after in-service inspection of the reactor pressure vessel undertaken by EDF; and what assessment she has made of the implications for that process of hydrogen flaking present in the RPV Doel 3 and Tihange 2 reactors in Belgium. more like this
tabling member constituency Newport West more like this
tabling member printed
Paul Flynn more like this
uin 39427 more like this
answer
answer
is ministerial correction false more like this
date of answer less than 2016-06-09more like thismore than 2016-06-09
answer text <p>During Sizewell B’s periodic shutdown, inspectors from the Office for Nuclear Regulation (ONR) examined the Licensee’s arrangements for maintenance activities, reviewed test and inspection records and inspected the plant and equipment. A thorough examination (or in-service inspection) of the reactor pressure vessel (RPV) was completed by EDF to confirm that it remains in good condition. An ONR team of technical specialists examined the results of the in-service inspections and they are satisfied that they demonstrate the continued integrity of the RPV and that the hydrogen flaking present in the Doel 3 and Tihange 2 reactors in Belgium is not evident at Sizewell B.</p><p> </p><p>ONR inspectors did not identify any issues that would affect the safety case for the restart of the Sizewell B reactor and its safe operation up to the next planned statutory periodic shutdown in 2017, and issued clearance for it to restart on 31 May 2016. ONR expects to publish its Project Assessment Report, detailing this decision, on its website.</p>
answering member constituency South Northamptonshire more like this
answering member printed Andrea Leadsom more like this
question first answered
remove filter
answering member
4117
label Biography information for Andrea Leadsom more like this
tabling member
545
label Biography information for Paul Flynn more like this